96”
5.
Complete all large and small frame attachments.
Screw each completed section together with
8 - 2 1/2” screws.
6.
When completed, your floor footprint
should be 136 1/2” Deep x 96” Wide.
136 1/2”
3.
Lay out
Floor Joist Frames
as illustrated.
There are 3 larger and 3 smaller Frame Sections.
The Footprint for the floor when attached together
will be 136 1/2” Deep x 96” Wide.
4.
Attach each large and small floor joist
frames together with
6 - 2 1/2” screws
per section.
Hardware (Step 4)
S1
- 2 1/2” Screws
x 18 total
Hardware (Step 5)
S1
- 2 1/2” Screws
x 16 total
Material used for Floor Runners are
not graded for appearance. Some
defect is allowed.
7.
Attach
Floor Runners
to completed floor frame.
There are 2 floor runners per 136 1/2” side and 5
completed runners in total. Use
6 - 2 1/2” screws
per completed Runner.Make sure Runners are flush
with edge of floor framing, but not overhanging.
Parts (Steps 7)
Floor Runners
(1 1/2” x 3 1/2” 68 3/16”)
x 10
Hardware (Steps 7)
S1
- 2 1/2” Screws
x 30 total