34.
Place second completed Rafter Section on Gable Walls as per
Steps 32 - 33
.
35.
At the peak, align Ridge Boards so they are flush together and secure
them with 12 - 1 1/4” screws. To completely secure Ridge Boards, place
4 - 1
1/4” screws
into any of the remaining
Metal Ridge Board Connector
holes.
Complete both sides.
Important:
If there is a gap between
Ridge Boards
, try
pushing side walls closer together from outside. Walls should be 91” apart at
top from inside of wall plate to wall plate.
Hardware (Step 35)
S2
- 1 1/4” Screws
x 16 total
Offset Metal Ridge
Board Connectors
Important:
If gable framing does not line up with Rafters, remove temporary 2” screws from
Gable framing. Re-align gable and secure with 8 - 2” screws total.
36.
With both
Ridge Boards
connected, completely secure
Rafters
to
Gable
framing of both
Gable Walls
. Use
8 - 2” screws
per gable.
Hardware (Step 36)
S3
- 2” Screws
x 32 total
Toll Free 1-888-658-1658 www.outdoorlivingtoday.com [email protected]
Page 23