© NOVATEC, Inc, 2018 All Rights Reserved 18 Document: SVP IM 7 FEB 2018
12 MAINTENANCE AND INSPECTION SCHEDULE
It is recommended that maintenance and inspection is done on a scheduled basis.
Maintenance requirements will naturally vary widely for each installation and specific
operating conditions. It is suggested that a complete inspection be performed with the
necessary maintenance at the end of the first day, the first week, the first month and the first
3 months. These inspections will be indicative of how often future maintenance will be
necessary.
12.1 EVERY WEEK
Inspect the Filter cartridge. Clean or replace as required. Remove any fines collected
from the catch pan. This time interval should be shortened if experience indicates
unusual dust loading. Check the system for air leaks and correct as required.
12.2 EVERY MONTH
Inspect the vacuum breaker valve filter/silencer. Clean or replace as required.
If service to the vacuum breaker is required remove it from the filter housing.
Filter Element in ClearVu Canister