3 INSTALLATION
3.1 Mounting The Dryer
Mount the NovaDrier to the processing machine (if machine mounted). Use the control
panel support bracket supplied on the bottom of the control box, as
the control box must be
supported properly
.
CAUTION: FOLLOW ALL NATIONAL AND LOCAL ELECTRICAL AND MECHANICAL CODES,
AS REQUIRED. ONLY QUALIFIED AND TRAINED PERSONEL SHOULD INSTALL AND
OPERATE THIS EQUIPMENT
3.2 Connecting Power
Refer to the specifications in Section 2 and the mechanical and electrical drawings
provided.
Connect the required electrical power to the unit through a main line
disconnect (field supplied) as indicated on the NOVATEC nameplate,
which is located on the side of the control box. Because the
controllers and various sensors are sensitive to “Industrial Noise”
the
system must be properly connected to true earth ground.
This is the
only power connection necessary as the system is completely pre-
wired.
Main power connection inside
control panel
NovaDrier machine
mounting.
Control panel support
bracket.
(Must be installed)