OPERATION AND MAINTENANCE MANUAL SL III ORIGINAL INSTRUCTION
Norlok Technology Inc.
519-759-5896
fax 519-759-2948
Page
|
9
Document No: 110011
Rev. No: 5.0
SECTION 3.0 - INSTALLATION AND OPERATION
INSTALLATION
UNCRATING:
1.
The press can be lifted using the forklift cutouts in the stand, using a
¾”NC
eye bolt inserted into the top of the
frame or using a chain hoist near the centre of mass which is in line wit
h the ¾” hole on the top.
2.
Locate the following items that may have been packed separately;
a)
Manual
b)
Laser pointer (if ordered)
c)
Spare punch and die
d)
Foot Pedal
3.
Check the condition of the press and record the serial number for reference.
SERIAL #
__-____
LEVELING AND BOLTING DOWN MACHINE:
I.
Level the machine
II.
Lag the machine to the ground if necessary.
INSTALLING AIR SUPPLY:
1.
Make sure that the foot pedal is not activated.
2.
Make sure that the main air supply valve is turned OFF.
3.
Supply the inlet with 125 psi (max) - 80 psi (min) of clean dry air. Use an additional filter / regulator on
the inlet line if necessary. We recommend a minimum of 1/2" diameter airline.
CAUTION TOP HEAVY
Fa