![NetApp H410S Hardware Information Download Page 8](http://html1.mh-extra.com/html/netapp/h410s/h410s_hardware-information_1669954008.webp)
•
H410S
Steps
1. Install the H410S nodes in the chassis. Here is a rear-view example of a chassis with four nodes installed:
Use caution while lifting the hardware and installing it into the rack. An empty two rack unit
(2U), four-node chassis weighs 54.45 lb (24.7 kg) and a node weighs 8.0 lb (3.6 kg).
2. Install the drives.
3. Cable the nodes.
If the airflow vents at the rear of the chassis are blocked by cables or labels, it can lead to
premature component failures due to overheating.
◦
Connect two CAT5e or higher cables in ports A and B for management connectivity.
◦
Connect two SFP28/SFP+ cables or transceivers in ports C and D for storage connectivity.
◦
(Optional, recommended) connect a CAT5e cable in the IPMI port for out-of-band management
connectivity.
4. Connect the power cords to the two power supply units per chassis and plug them into 240V PDU or power
outlet.
5. Power on the nodes.
It takes approximately six minutes for the node to boot.
H610S
Steps
1. Install the H610S chassis. Here is an illustration for installing the node/chassis in the rack:
6