14
Redundant Power Upgrade Kit Installation Procedures
Installing the LED/Switch Assembly
Install the new LED and presence switch assembly in the server as follows.
1.
Insert the top and bottom power supply LED/switch assembly modules as
shown in the following figure. In the following two figures match
A
to
A
and
B
to
B
.
Installing the Top and Bottom LED/Switch Assembly Modules
2.
Cable the top and bottom power supply LED/switch assembly modules
exactly as stated below and as shown in the following figure.
Top PSU LED Cable Connector (Single Cable) — Plugs into connector J7
on the power controller board.
Bottom PSU LED Cable Connector (Single Cable) — Plugs into connector
J2 on the power controller board.
Data Cable Connector (Double Cable) — Plugs into connector J7 on the
SCSI backplane. Remove the jumpers plugged into J7.
Secure the loose cables by attaching and using the two "Cable Keeps" (C),
as shown in the above figure. The "Cable Keeps" are attached by peeling the
backing off the adhesive and sticking them to the appropriate location on the
side of the chassis.