8 Site Preparation
Customer Responsibilities
Before the system can be installed, the customer must do or provide the
following:
•
When required by NCR, provide the NCR Customer Services
representative with appropriate drawings that indicate:
•
Location of the equipment
•
Site wiring (power and communications, paths and lengths)
•
Location of other equipment that may generate electrical noise,
electromagnetic interference, or heat
•
Make building alterations necessary to meet wiring and other site
requirements
•
Provide and install all communications cables, wall jacks, special
connectors, and associated hardware
•
Provide and install necessary power distribution boxes, conduits, grounds,
lightning protection devices, and associated hardware
•
Make sure all applicable codes, regulations, and laws (including, but not
limited to, electrical, building, safety, and health) are met
•
Provide and install auxiliary power or other equipment as required
•
Provide storage or service areas as required
•
Meet all system/ unit environmental requirements
•
Provide and install floor coverings and environment systems that limit or
control static electricity build-up and discharge
In general, keep the NCR equipment area free from dust, smoke, lint, and other
particles. Restrict smoking, eating, and drinking around the equipment. Avoid
location the equipment near other machines that generate ink, carbon, and paper
dust particles.
Finally, only the customer can know the full extent of the damage that may be
caused to his/ her business by reason of failure of the equipment that is to be
installed. For this reason, it is the customer’s responsibility to ascertain the
extent of any such possible damage to his/ her existing or planned business, and
to effect full insurance in respect of it.
Summary of Contents for 7448 Workstation
Page 1: ...NCR 7448 Workstation Release 1 3 Site Preparation B005 0000 1201 Issue D...
Page 12: ......
Page 15: ...Site Preparation 3 7448 Workstation with 80 Key Conventional Keyboard...
Page 39: ...Site Preparation 27 245 mm...
Page 41: ...Site Preparation 29 NCR 2182 Cash Drawer...
Page 57: ...Site Preparation 45...
Page 58: ......