![Nautel NV15LT Installation Manual Download Page 39](http://html1.mh-extra.com/html/nautel/nv15lt/nv15lt_installation-manual_711198039.webp)
NV20LT/NV15LT INSTALLATION MANUAL
INSTALLING PROGRAM INPUTS
VERSION 4.0 2018-02-26
PAGE 2.7.1
SECTION 2.7: INSTALLING PROGRAM INPUTS
This section describes how to route program input wiring to the NV20LT/NV15LT’s exciter(s).
Planning Complete?
1.
Make sure you have read and fully understood the program input options described in the NV20LT/
NV15LT Pre-installation Manual before proceeding.
2.
Make sure the program input wires are long enough to allow routing through the top of the
transmitter cabinet and down to the rear panel of the controller and exciter (if applicable).
3.
If you ordered the optional Exciter Upgrade kit, make sure it is installed (see
“Upgrading to Dual
Exciter” on page 2.3.5
). The transmitter is factory configured with a single exciter - within the
controller (A4).
4.
If you ordered the optional Orban Inside Audio Processor kit for one or both exciters, as applicable,
make sure it is installed (see
“Installing the Orban Inside Card” on page 2.3.8
). The transmitter’s
exciters are factory configured with no Orban Inside audio processor card.
Routing Cables
Route the desired analog and digital program input cables to the back of the NV20LT/NV15LT’s
controller and optional exciter.
1.
Route all program input cables from their audio sources to the top of the transmitter. If you are
using dual exciters, you will need two sets of program inputs - one for each exciter.
2.
Get two ferrite toroids (Nautel Part # LXP38, 19 mm inner diameter) from the ancillary kit for each
exciter installed. The controller’s integral exciter is exciter A. The optional exciter, if installed, is
exciter B.
3.
Pass all program input cables through the ferrite toroids obtained in
Step 2
. If practical, wires
should pass through a minimum of two times (two turns) (see
Figure 2.7.1 on page 2.7.2
). An
entrance is provided at the top of the transmitter to accept program input wiring. Position the
ferrite toroids just outside, or just inside, the program input entry hole.
4.
Punch the appropriate size hole in the program input entry plate (see
Figure 2.7.2 on page 2.7.3
):
Remove the program input entry plate from the top of the transmitter. It is secured using four
M4 screws and has a pre-cut, centered 1/4-inch diameter hole.
Summary of Contents for NV15LT
Page 2: ......
Page 4: ......
Page 8: ...NV20LT NV15LT INSTALLATION MANUAL PAGE 2 VIII VERSION 4 0 2018 02 26...
Page 18: ...NV20LT NV15LT INSTALLATION MANUAL UNPACKING AND POSITIONING PAGE 2 2 8 VERSION 4 0 2018 02 26...
Page 26: ...NV20LT NV15LT INSTALLATION MANUAL INSTALLING OPTIONS PAGE 2 3 8 VERSION 4 0 2018 02 26...
Page 36: ...NV20LT NV15LT INSTALLATION MANUAL CONNECTING AC POWER PAGE 2 5 6 VERSION 4 0 2018 02 26...
Page 42: ...NV20LT NV15LT INSTALLATION MANUAL INSTALLING PROGRAM INPUTS PAGE 2 7 4 VERSION 4 0 2018 02 26...
Page 60: ...NV20LT NV15LT INSTALLATION MANUAL COMMISSIONING PAGE 2 9 12 VERSION 4 0 2018 02 26...
Page 64: ...NV20LT NV15LT INSTALLATION MANUAL PARTS AND TOOLS PAGE 2 10 4 VERSION 4 0 2018 02 26...
Page 76: ...NV20LT NV15LT INSTALLATION MANUAL LIST OF TERMS PAGE 2 12 2 VERSION 4 0 2018 02 26...
Page 77: ......