NV10LT/NV7.5LT INSTALLATION MANUAL
COMMISSIONING
PAGE 2.9.8
VERSION 5.0 2021-03-01
Going On-Air
IMPORTANT!
Before going on the air, if you want the safety interlocks to operate properly, the
shorting jumpers installed in
“Pre-Commissioning Tasks” on page 2.9.2
should be removed.
1.
Turn off the power using the ac disconnect switch, if one is being used, or else at the ac source.
2.
Connect the transmitter's RF output to an antenna system (or verify that the current connection is
intact).
3.
Turn the transmitter’s ac power back on.
4.
Use the front panel UI to begin transmitter operations. For detailed instructions, refer to the
NV10LT/NV7.5LT Operating and Maintenance Manual.
Set for desired power level.
Press the front panel’s
RF On
pushbutton switch.
Select the desired exciter as main, if applicable.
WARNING! If a jumper is placed between the INTLK inputs [pins 19 and 20
of the controller’s REMOTE I/O-A connector (A1J2A) or TB1-1 and 2 on the
optional remote interface PWB], safety features controlled by the external
interlocks will be disabled. A fail-safe method of alerting personnel to this
fact should be implemented. Voltages which are dangerous to life will be
present on the RF output stages and the antenna system if the transmitter
is turned on.
Summary of Contents for NV10LT
Page 2: ......
Page 4: ......
Page 8: ...NV10LT NV7 5LT INSTALLATION MANUAL PAGE 2 VIII VERSION 5 0 2021 03 01...
Page 36: ...NV10LT NV7 5LT INSTALLATION MANUAL INSTALLING PROGRAM INPUTS PAGE 2 7 4 VERSION 5 0 2021 03 01...
Page 54: ...NV10LT NV7 5LT INSTALLATION MANUAL COMMISSIONING PAGE 2 9 12 VERSION 5 0 2021 03 01...
Page 58: ...NV10LT NV7 5LT INSTALLATION MANUAL PARTS AND TOOLS PAGE 2 10 4 VERSION 5 0 2021 03 01...
Page 68: ...NV10LT NV7 5LT INSTALLATION MANUAL LIST OF TERMS PAGE 2 12 2 VERSION 5 0 2021 03 01...
Page 69: ......