BUILD

 

8

 

FIGURE S

 

F1

 

 Anchor plates can be mounted with either a bolt or screw depending on the 
sub–

 

floor. See table 

(Figure S) 

for recommended hardware for various floor 

types. If there are any questions concerning floor types, consult an architect or structural 
engineer.

 

Note 1: 

Anchor plates can be 

mounted in any position about the 
glide to which they are attached.  

 

Note 2: 

There are two mounting 

locations on the anchor plate. The 
thru hole is sized for #8 screws and 
the slot is sized for 

1/4” 

bolts and 

screws, as described in the 
recommended fastener table below.

 

Note 3: 

To minimize visual impact of required anchors, align the anchor plate in

-

line and 

directly underneath the cross

-

bar of the sub

-

assembly frame section, that runs front to 

back. A bolt is required in this scenario as there is wrench access only.

 

F2

 

With frame in final installed location, position the anchor plates where they are 
to be installed. 

 

Note: 

If joining multiple units with a ganging kit, build and position all frames in their 

final location, then install ganging kits prior to anchoring.

 

F3

 

Mark locations to drill out pilot holes for each of the anchor plates. 

 

F4

 

Move frame out of the way and drill appropriate pilot holes for the fastener 
selected. (If applicable) start concrete anchors into pilot holes.

 

 

F6

 

Install anchor fasteners to clamp down anchor plates and finish the installation. 
The frame is ready for use at this point.

 

 

F5

 

Reposition frame back into final installation location. Check that the frame is 
still level and adjust if necessary.  

 

Note 3: 

Align 

under frame

 

Note 2: 

Thru hole

 

Note 2: 

Slot hole

 

Note 1: 

One anchor plate mounted 

in any position about the axis of the 

FIGURE R

 

Summary of Contents for LOCHLYN

Page 1: ...instructions before using this product Failure to follow the instructions and safety precautions in this manual can result in injury or damage to equipment KEEP THIS MANUAL IN A SAFE PLACE FOR FUTURE...

Page 2: ...ss and identification in the later steps of assembly Figure A Model Assembly Instruction Sheet Model AI Sheet includes frame dimension references and parts list for specific model 2Select a frame sub...

Page 3: ...s noted in step 3 There shouldn t be any remaining junction blocks from the hardware bag or open 3 hole patterns after these steps are complete Figure G 6Retrieve the Model AI Sheet with image of asse...

Page 4: ...re are different length horizontal bars from one column to the next Reference the Model AI Sheet to determine which length bar is correct CAUTION Do not deviate from the provided Model AI Sheet and in...

Page 5: ...evels until all junction blocks are fully secured to the horizontal bars of the frame The vertical sub assembly should be flush with the horizontal bars of the frame Figure K Note While assistance is...

Page 6: ...their midpoint CAUTION Do not extend glides beyond 13mm 0 5in from the glide s fully retracted position Extending glides more than 13mm 0 5 in can make the shelving unit unstable If installing a one 1...

Page 7: ...drawers above three 3 tiers can lead to instability and injury from unit tipping over Floor Anchoring Method All frames will have at least four 4 anchor plates mounted to the floor glides on both end...

Page 8: ...impact of required anchors align the anchor plate in line and directly underneath the cross bar of the sub assembly frame section that runs front to back A bolt is required in this scenario as there i...

Page 9: ...studs must be C channel 20 gauge thick minimum Metal or wood studs must be on centers no greater than 24 and have maximum height of 14 restrained at floor and ceiling Interior walls shall be designed...

Page 10: ...Reference fastener table Figure V for recommended hardware for various wall construction types Select the hardware and install to the wall using all of the wall anchors provided following the next ste...

Page 11: ...tionalOfficeFurniture com 3248959 Rev B LOCHLYN FREESTANDING FRAME BUILD 11 W4Mark the wall to locate the wall brackets vertically in line with the frame tubing or horizontally where necessary to reac...

Page 12: ...nal installation position so all mounting brackets are in line vertically or horizontally based on required installation orientation Check that the frame is still level and wall anchor brackets align...

Reviews: