NI TB-9214 Calibration Procedure

Initial Setup

Complete the following steps to set up the NI TB-9214.
1.

Install NI-DAQmx.

2.

Make sure the NI cDAQ-9178 power source is not connected.

3.

Connect the NI cDAQ-9178 to the system safety ground.
a.

Attach a ring lug to a 14 AWG (1.6 mm) wire.

b.

Connect the ring lug to the ground terminal on the side of the NI cDAQ-9178 using 
the ground screw.

c.

Attach the other end of the wire to the system safety ground.

4.

Install the NI 9214 in slot 8 of the NI cDAQ-9178 chassis. Leave slots 1 through 7 of the 
NI cDAQ-9178 chassis empty.

5.

Connect the NI cDAQ-9178 chassis to your host computer.

6.

Connect the power source to the NI cDAQ-9178 chassis.

7.

Launch Measurement & Automation Explorer (MAX).

8.

Right-click the device name and select 

Self-Test

 to ensure that the module is working 

properly.

Verification

The following performance verification procedure describes the sequence of operation and test 
points required to verify the NI TB-9214 and assumes that adequate traceable uncertainties are 
available for the calibration references.

Terminal Block CJC Verification

Complete the following procedure to determine the As-Found status of the NI TB-9214.
1.

Loosen the captive screws and remove the top cover from the NI TB-9214.

2.

Connect the thermocouple calibrator to the NI TB-9214 using the barrier strip assembly 
created in the 

Building the Barrier Strip Assembly

 section. Refer to Figure 3 for a 

connection diagram.

Summary of Contents for NI TB-9214

Page 1: ...ts Software 1 Documentation 2 Test Equipment 3 Building the Barrier Strip Assembly 4 Test Conditions 5 Initial Setup 6 Verification 6 Terminal Block CJC Verification 6 Where to Go for Support 9 Softwa...

Page 2: ...ons and Specifications NI TB 9214 specific information specifications and calibration interval NI DAQmx Readme Operating system and application software support in NI DAQmx LabVIEW Help LabVIEW progra...

Page 3: ...Module Use an NI 9214 module that is verified to be within product specifications Chassis NI cDAQ 9178 BarrierStrip Assembly Thermocouple Wire TT E 24 SLE 100 E type SLE 24 AWG 20 to 30 meters Thermo...

Page 4: ...Crimp the chromel spade lugs to the chromel wire to create 16 positive spade lugs Crimp the constantan spade lugs to the constantan wire to create 16 negative spade lugs 2 Use the thermocouple wire sp...

Page 5: ...I TB 9214 meets published specifications Keep connections to the NI TB 9214 as short as possible Long cables and wires act as antennae picking up extra noise that can affect measurements Verify that a...

Page 6: ...er 6 Connect the power source to the NI cDAQ 9178 chassis 7 Launch Measurement Automation Explorer MAX 8 Right click the device name and select Self Test to ensure that the module is working properly...

Page 7: ...temp0 value a Create and configure an AI Temp Built In Sensor task for CJC channel _cjtemp0 on the NI 9214 according to Table 2 b Configure the AI Temp Built In Sensor task for CJC channel _cjtemp0 ac...

Page 8: ...fore acquiring data Wait at least 300 ms for the Ectron 1140A to settle before acquiring data with the NI 9214 Disregard the first six seconds of the acquisition to compensate for the open thermocoupl...

Page 9: ...at the NI TB 9214 is outside of the limits refer to Where to Go for Support for assistance in returning the device to NI Where to Go for Support The National Instruments Web site is your complete reso...

Reviews: