3.8 minimum clearance to combustibles
As long as clearance to combustibles is kept within the required distances, the most desirable and beneficial
location for a Napoleon® appliance is in the centre of a building, thereby allowing the most efficient use of the
heat created. The location of windows, doors and the traffic flow in the room where the appliance is to be located
should be considered. If possible, you should choose a location where the vent will pass through the house with-
out cutting a floor or roof joist.
MINIMUM CLEARANCE TO COMBUSTIBLES MUST BE MAINTAINED OR A SERIOUS FIRE HAZARD
COULD RESULT.
FRAMING OR FINISHING MATERIAL CLOSER THAN THE MINIMUMS LISTED MUST BE CONSTRUCTED
ENTIRELY OF NON-COMBUSTIBLE MATERIALS (I.E. STEEL STUDS, CEMENT BOARD, ETC.).
NEVER OBSTRUCT THE FRONT OPENING OF THE APPLIANCE.
!
WARNING
4.8 MINIMUM CLEARANCE TO COMBUSTIBLES
As long as clearance to combustibles is kept within the required distances, the most desirable and bene
cial
location for a Napoleon® appliance is in the centre of a building, thereby allowing the most ef
cient use of
the heat created. The location of windows, doors and the traf
c
ow in the room where the appliance is to be
located should be considered. If possible, you should choose a location where the vent will pass through the
house without cutting a
oor or roof joist.
A.
4” (102mm)
B.
2” (51mm)*
C.
2” (51mm)
To ceiling from appliance top
48” (1219mm)
Horizontal vent
Sides and bottom
1” (25mm)
Top
2”
(51mm)
Vertical vent
All
sides 1”
(25mm)
*At a distance of 2” (51mm) from the wall, installation or service to the blower may not be practical. A minimum
of 5” (127mm) will be required in order to install the blower.
If less than 5” (127mm) clearance is maintained between the back of the appliance and the back wall, it will be
necessary to disconnect the venting and gas pipe to move the appliance out for installation or service of the
blower.
W415-1332 / A / 11.21.14
24
EN
A.
4” (102mm)
B.
2” (51mm)*
C.
2” (51mm)
To ceiling from appliance top
48” (1219mm)
Horizontal vent:
Sides and bottom
1” (25mm)
Top
2”
(51mm)
Vertical vent:
All
sides
1”
(25mm)
*At a distance of 2” (51mm) from the wall, installation or service to the blower may not be practical. A minimum of
5” (127mm) will be required in order to install the blower.
If less than 5” (127mm) clearance is maintained between the back of the appliance and the back wall, it will be
necessary to disconnect the venting and gas pipe to move the appliance out for installation or service of the
blower.
• Minimum clearance to combustibles must be maintained or a serious fire hazard could result.
• Framing or finishing materials closer than the minimums listed must be constructed entirely of non-com-
bustible materials (i.e. steel studs, cement board, etc.).
• Never obstruct the front opening of the appliance.
!
WARNING
EN
W415-2207 /
C
/
08.23.18
24
installation