background image

 

 

 

 

14

 

Installation and operation manual

DTH-V9-2020 

 

 
 

 
 
Depending  on  the  model,  the  flue  vent  connector  diameter  ranges  from  6  to  10  inches.  The  DTH 
model series is designed to operate effectively and safely (against a positive pressure of 0.25 in.w.c) 
with  a 

positive  stack  (category  III)  type

  sealed  single  wall  or  double  wall  flue  vent 

listed

  for  this 

application,  whether  vertical  arrangement  or  horizontal  or  a  combination  of  both.  The  minimum 

diameter  of  all  sections  must  be  identical  to  the  unit’s  connection  diameter

  or  greater. 

Do  not 

intermix  different  listed  vent  system  parts  from  different  manufacturers  in  the  same  venting 
system. 

 

A  listed  vent  cap  or  termination  of  the  same  diameter  as  the  exhaust  pipe  must  be  used  at  the 
extremity  located  at  the  exterior  of  the  building  (see  drawings  below).  See  pictures  below  for 
recommended end cap and configurations. The exhaust pipe must end at the exterior of the building 
while respecting (at least but not limited to) the following clearances: 

 

 Clearances for vent terminals ** 

Structure 

Minimum Vent Terminal Clearances*** 

Motorised air intake less than 1.8m (6’)

 

0.9m (3’) above and 1.8m (6’) to the side

 

Combustion air intake from another device  

1.8m (6’) above and 1.8m (6’) to the side

 

Door, openable window, revolving door or 
all other openings 

1.8m (6’) to the side

 

0.9m (3’) above

 

Electrical or gas meter, regulator and relief 
equipment * 

1.8m (6’) to the side (Canadian standards)

 

1.2m (4’) to the side (U.S.A. standards)

 

Vent outlet from another service 

0.9m (3’) 

 

Building or adjacent wall or parapet 

1.8m (6’)

 (might have to be increased for horizontal 

discharge) 

Sidewalk or parking lot  

2.1m (7’) above

 

Ground vent 

0.3m (1’) above snow level

 

Wall of vent outlet 

0.3m 

(1’) minimum

 

Roof of vent outlet 

0.9m (3’) minimum and 0.6m (2’) above all obstacles 
less than 3m (10’) 

 

Never install a flue vent outlet above a service regulator or a gas meter. 

**  Local codes always supersede the above provisions. 
***  Take all necessary precautions to avoid the installation of vent outlets where snow accumulation 

can  occur  naturally  or  due  to  roof  snow  slides  or  snow  removal  dumps.  In  the  case  of  a 

horizontal  exhaust,  a  secure  distance  of  3m  (10’)  must  be  added  to  the  distance  f

ound  in  the 

table for horizontal direction, measured from the mechanical or gravity air intakes. 

 

The flue vent must be built using a category III listed vent pipe system sealed corrosion resistant steel 
pipe having a minimum thickness of 24 gauge or heavier, in the interior of the building. However, a 
double-wall  corrosion  resistant  pipe  section  is  required  to  get  through  the  external  walls  of  the 
building  to  the  vent  cap  (consult  vent  pipe  supplier  instructions).  Make  sure  to  have  provision  for 
combustion testing port close to the unit for verifications and adjustments. 

 

Flue vent and combustion air 

 

Summary of Contents for DTH Series

Page 1: ...DTH V9 2020 DTH Series Installation Outdoor Indoor INSTALLATION AND OPERATION MANUAL 1385 Lionel Boulet blvd Varennes Quebec Canada J3X1P7...

Page 2: ...cause serious injury death or property damages Do not store or use gasoline or other flammable vapors and liquids in the vicinity of this or any other appliance WHAT TO DO IF YOU SMELL GAS o Do not tr...

Page 3: ...dow 27 Level 1 Air Gas relation 28 Level 1 Alarm history 29 Level 2 Fan RPM auto tuning 30 Level 2 Signal supervision 31 Level 2 Step timer 32 PLC alarms 33 Flame safeguard alarms 34 Flame safeguard t...

Page 4: ...floor Allocate enough space around the unit for maintenance and around the combustion air intake and the inlet air hood to prevent harmful accumulation of snow Clearances to combustible materials Posi...

Page 5: ...gh pressure regulator must be installed at gas piping inlet The regulator must be suitable for modulation ratio of 40 1 to properly regulate gas pressure at low fire The regulator vent must be piped s...

Page 6: ...0 17 6 150 3 9 0 97 150 10 2 5 14 3 5 4 0 0 99 The pressure adjustment may vary slightly See the unit name plate for the exact value With optional 2 NPT gas train With standard 1 1 2 NPT gas train At...

Page 7: ...n facing air stream Unit dimensions WARNING Improper installation adjustment alteration can cause serious injury death or property damages Note The controls shown are on the left hand side of the unit...

Page 8: ...al DTH V9 2020 DTH Vertical discharge Left hand control when facing air stream Note The controls shown are on the left hand side of the unit for a right hand unit the drawing is mirrored and dimension...

Page 9: ...4 F 19 21 25 27 28 32 32 32 37 37 E 8 7 8 8 7 8 8 7 8 8 7 8 8 7 8 8 7 8 8 7 8 8 7 8 8 7 8 8 7 8 S 45 45 45 45 51 51 56 1 2 56 1 2 56 1 2 72 NN 18 1 4 20 1 4 24 1 4 26 1 2 27 1 2 29 27 25 35 35 Dim Me...

Page 10: ...g on the model the flue vent connection diameter ranges from 6 to 10 inch The DTH models are designed to operate effectively and safely with a positive stack category III type sealed single wall or do...

Page 11: ...s essential for the proper operation of the unit Improper positioning of the supply temperature sensor could result in high temperatures in the supply ducts a thermal protection shutdown the closing o...

Page 12: ...g diagram for remaining wiring connections Main 120V 60Hz 1ph ac power supply see wiring diagram for current On Off contact for heating demand This heating demand must be wired in series with at least...

Page 13: ...h screen interface 2 Programmable logic controller PLC 3 Heating element 4 Input output expansion module I O 5 Ignition transformer 6 High limit protection set at 160oF 7 Flame safeguard module 8 Ther...

Page 14: ...ff valve 1 7 Valve proving system with IRI option 8 Main gas safety shutoff valve 2 9 Modulating gas valve actuator 10 Modulating gas valve 11 Low fire orifice bypass 12 Test firing gas valve 13 High...

Page 15: ...8m 6 to the side 0 9m 3 above Electrical or gas meter regulator and relief equipment 1 8m 6 to the side Canadian standards 1 2m 4 to the side U S A standards Vent outlet from another service 0 9m 3 B...

Page 16: ...ss insulator able to withstand temperatures of 288 Celsius 550F In certain conditions these units can produce condensate This corrosive liquid must be treated and drain correctly with provision to pre...

Page 17: ...16 Installation and operation manual DTH V9 2020 Recommended roof top Flue Vent Exhaust and or Combustion Air Duct Recommended wall horizontal Flue Vent Exhaust and Combustion Air Duct Concentric kit...

Page 18: ...of straight sections of the flue vent to the equivalent length of all the elbow pipes used A 90 degree elbow pipes has an equivalent length of 3m 10 and a 45 degree angle elbow pipes has an equivalent...

Page 19: ...tification section for location Ensure that the gas inlet pressure complies with the following value Standard inlet pressure Natural Gas Propane LP Minimum 7in w c 1 74 kPa 11in w c 2 74 kPa Maximum 1...

Page 20: ...excess air Compare the manifold pressure with the name plate indication Adjust the gas regulator if needed to obtain the right value At high fire you should have a combustion reading of 3 5 O2 approx...

Page 21: ...t is above 2 3 VDC the safety verification is enabled Step 2 Safety verification S20 S25 The burner air proving switch PAB1 is verified during the two following tests 1 Activation of the air proving s...

Page 22: ...begin Modulating gas valve and the blower follow the request signal value According to the gas valve position the blower modulates following an air gas relation curve pre set into the PLC memory to a...

Page 23: ...imately in order to purge the heat exchanger After the post purge delay the sequence returns to the standby step But if an alarm is active a manual reset is required on the HMI touch screen When the a...

Page 24: ...LEDs I O states Digital inputs relay outputs and fast output LEDs 6 USB mini B port For terminal connection to a computer for programming need SoMachine program 7 Clip on lock For 35mm 1 38 in top ha...

Page 25: ...ng port 17 Locking hook Hook not included PLC status LEDs description 1 System status LEDs Label Function Color Description PWR Power Green On Power is applied RUN Machine status Green On Valid applic...

Page 26: ...t Stop Burner request by others I6 Burner air proving switch Alarm I7 Flue vent back pressure Alarm I8 Burner On status proof relay I9 Air Intake low pressure Alarm I11 Valve proving system relay with...

Page 27: ...manual DTH V9 2020 The following diagram describes the structure of different levels in the HMI Display HMI features Home page Run window Level 1 menu Level 3 menu Password protected Level 4 menu Pas...

Page 28: ...llowing a linearization curve and the air blower will follow the gas valve feedback position with the correspondent value determined in the fan modulation table 1 Heat Heating demand signal VDC 2 Gas...

Page 29: ...raphic Fan modulation curve for each 0 5 V of gas valve position The vertical rectangle shows the position you have selected for modification If the unit is running vertical and horizontal dashed line...

Page 30: ...codes The number 1 being the most recent code 1 Code The alarm code number is related to an alarm type first digit and in which steps it s happened second digit See PLC Alarms section for details 2 E...

Page 31: ...is possible only if the demand contact I5 on the PLC is open not activated At the end of the process a confirmation will be asked see item 4 2 Fan command in 3 rpm Fan rpm feedback during the process...

Page 32: ...s Gas valve modulation signal demand first row and actual position feedback signal second row Expressed in volt V Can be different to Heat command 3 Air Burner air blower modulation demand first row a...

Page 33: ...ive In this example the prepurge step is now at 6 seconds on a 40 seconds timer 1 Actual count Timer count in real time sec 2 Maximum Maximum value of the count In some situation it s a goal or it s a...

Page 34: ...on the flame safeguard Flame safeguard in alarm see next section Fan feedback lost Combustion air fan feedback signal is missing during 40 Burner ignition step 4 41 Flame stabilization step 5 42 Modul...

Page 35: ...Trouble code Trouble description alarms Red Lights OPR CTRL Air flow PTFI Flame Alarm 6 Frequency noise O O 7 Pilot flame failure PTFI O 19 Burner flame failure MTFI O O 21 Lockout Interlock open O 5...

Page 36: ...temperature maximum temperature safety switch opens at 160 F Verify the temperature sensor position need to read average temperature Verify burner modulation all controls and temperature signal Verify...

Page 37: ...36 Installation and operation manual DTH V9 2020 Typical wiring diagram TYPICAL WIRING DIAGRAM TYPICAL WIRING DIAGRAM TYPICAL WIRING DIAGRAM...

Page 38: ...37 Installation and operation manual DTH V9 2020 TYPICAL WIRING DIAGRAM...

Page 39: ...ch in OFF position 2 Check fan belts and adjust or replace if necessary 3 Check the condition of filters and replace if necessary 4 Make sure nothing partially or completely obstructs the air inlet an...

Page 40: ...flammable materials near the unit Make sure that the combustion air inlet and flue vent are not blocked or obstructed Verify flame state and combustion Verify that all safety controls are operational...

Page 41: ...d damages caused by improper matching or applications of the product or the product s components e damages caused by failing to provide routine and proper maintenance or service to the product f expen...

Page 42: ...nt Top air baffle installed Low limit installed Condensate drain Note ______________________________________________________________________________________________ Start up Flame signal _________ VDC...

Page 43: ...____________________________________________________________ ___________________________________________________________________________________________________ _______________________________________...