Installation manual Infix ProLine
4. Planning the module field
4.1 Operating conditions
Module field planning is based on:
• Module size (L x W x H),
• Module positioning (portrait, landscape),
• Number of modules and
• Roof batten spacing
Additional roof battens
If the existing roof battens do not correspond to the required
points in the module field, additional roof battens will be
necessary at the following points:
• Fixation of upper adapters
• Fixation of the sealing strip
• Fixation of the top flashing
Additional roof battens and their respective fixing materials
are not included in delivery.
i
NOTE!
The following must be observed for
planning the module field:
• The standard Infix ProLine components
are designed for mounting the module
field into a tiled roof. Mounting on other
types of roof coverings must always be
done by a professional roofing
company.
• There must be a distance of at least
three rows of tiles between the top
edge of the module field and the roof
ridge. If this is not the case, the top
edge completion must be performed
by a roofing company to guarantee the
water tightness and durability of Theta.
• Should the ridge tiles not be fixed, then
there must be a distance of at least
one row of tiles between the top edge
of the module field and the roof ridge.
• Direct connections of the module field
to the roof ridge, roof verge or the
eaves must be performed by a
professional roofing company in all
cases.