–25–
(5)
Check points for system structure
Check points from installation work to test run.
Trouble
Not operate.
Not cool (at cooling).
Not heat (at heating).
Not cool, not heat, error stop.
Condensation drip in piping.
Not cool, not heat, error stop.
Water leak, condensation drip in drain piping.
Error stop, not operate.
Electric shock.
Error stop, not operate.
Classification
Installation and
piping
Power source
wiring
Portion
1
2
3
4
5
6
7
8
1
2
3
Check item
Instruction for selecting combination of outdoor unit,
and indoor unit followed? (Maximum number of indoor
units which can be connected, connecting model name,
and total capacity.)
Follow limitation of refrigerant piping length? For example,
70m (229ft) or less (total length : 220m (721ft)) at the farthest.
Connecting piping size of branch piping correct?
Refrigerant piping diameter correct?
Refrigerant leak generated at connection?
Insulation work for piping properly done?
Specified amount of refrigerant replenished?
Pitch and insulation work for drain piping properly done?
Specified switch capacity and wiring diameter of main
power source used?
Proper grounding work done on outdoor unit?
The phases of the L line (L1, L2, L3) correct?
Summary of Contents for PURY-100TMU
Page 8: ... 7 Controller Box ...
Page 11: ... 10 G A board CNIPM1 CN15V1 CNDR1 CNE CNDC1 Power board ...
Page 13: ... 12 RELAY 10 board RELAY 4 board ...
Page 14: ... 13 2 Refrigerant Circuit Diagram and Thermal Sensor ...
Page 15: ... 14 3 Electrical Wiring Diagram 1 MC P N ...
Page 17: ... 16 3 CMB 108 1010NU F ...
Page 18: ... 17 4 CMB 1013 1016NU F ...
Page 71: ... 70 Motor Compressor G A board Red U V W N P White Blue Blue Capacitor C1 Red IPM ...