Electric Connections Required for Start-Up
Normal precautions should be taken with regard to electrical components in the
vicinity of a water source.
Electrical Power Connection
The power cable to the OSG is run through the cooling compartment into the switch gear
compartment. The power cable enters the enclosure through the back of the cooling
compartment into conduit (Figure 4 & 5). Remove the switch gear cover by loosening the
screws in each corner (Figure 6) and pull the cable into the switch gear compartment. Route
the power cable to the top of the switch gear and wire the switch gear (Figure 7). Replace
the switch gear cover.
Do not Apply power to the system until installation is complete
Figure 4 Rear View of RIO OSG Showing Main Power Conduit
Conduit