4 Device installation
4.1 General notes
Before starting work, please read Chapter 2 and follow all instructions.
WARNING
Warning of hazardous area and/or personal injury
All cable connections must be protected from damage.
Note:
-
Measurement cables should be kept away from power equipment.
-
Signal cables and measurement cables should be installed separately from electric
power lines.
-
Measurement cables should be laid in separate cable conduits.
-
Network cables should be crossed perpendicularly.
Further procedures:
-
Check the consignment: make sure that all components are present.
-
Safety check: inspect all components for damage.
-
Make sure that the on-site installation is correct and complete including cables, e.g.
power cable fuse protection, load cells, junction box, data cables, console/cabinet,
etc.
-
Follow all device installation instructions related to application, safety, ventilation,
sealing and environmental inluences.
-
Connect the cable from the junction box or platform/load cell.
-
Connect additional data cables/network cables etc. as needed.
-
Connect the power supply.
-
Check the installation.
4.2 Mechanical preparationControl cabinet equipment
Have all required parts, technical documents, and tools at hand for control cabinet
installation.
Other procedure:
-
Make the control panel cut-out for the device in the control cabinet door, for
example; see Chapter
.
-
Install the device.
-
Remove the anchoring clamps.
-
Push the device with the seal attached from the front in to the switch table
recess.
4 Device installation
Remote display PR 5110/60, ../70