72
2. Pump drainage mode
2.1 Disconnect the plug of water level switch,
remove the cover of water test hole and slowly
infuse about 2000ml water through the water
test hole, be sure that the water will not touch
the motor of drainage pump.
2.2 Power on and let the air conditioner
operate for cooling. Check operation status
of drainage pump, and then connect the
plug of water level switch, check the
operation sound of water pump and
observe whether the water can discharge
through the transparent hard pipe at
drainage outlet. (In light of the length of
drainage pipe, water shall be discharged
about 1 minute delayed)
2.3 Stop the operation of air conditioner, power
off the power supply and put the cover of
water test hole back to the original place.
a. After stopped the air conditioner 3 minutes,
check whether there is anything abnormal.
If drainage pipes have not been distributed
properly, over back-flow water shall cause
the
flashing
of
alarm
indicator
at
remote-controlled receiving board and
even water shall run over the water
collector.
b. Continuously infusing water until water
level alarmed, check whether the drainage
pump could discharge water at once. If
water level does not decline under warning
water level 3 minutes later, it shall cause
shutdown of unit. When this situation
happens, the normal startup only can be
recovered by turning down power supply
and eliminating accumulated water.
Note:
Drain plug at the main water-containing
plate is used for eliminating accumulated water
in water-containing plate when maintaining air
conditioner fault. During normal operation, the
plug shall be filled in to prevent leakage.
12.5.4
Insulation work of drainage pipe
Refer the introduction to the insulation
engineering parts.
12.6 Vacuum Drying and Leakage
Checking
12.6.1
Purpose of vacuum drying
Eliminating moisture in system to prevent
the phenomena of ice-blockage and copper
oxidation.
Summary of Contents for MCHSU-09PHH2
Page 7: ...5 2 2 Part names of Indoor Outdoor units Cassette Unit...
Page 8: ...6 Duct Units...
Page 9: ...7 Console...
Page 10: ...8 Ceiling floor Units...
Page 28: ...26 Console Unit Ceiling floor Units 39 37 39 37in 3 94in 39 37in 1 38in...
Page 32: ...30 MEHSU 09CHN2 MEHSU 12CHN2 MEHSU 36CSC2 MEHSU 48CSC2...
Page 33: ...31 MEHSU 36CSD2 MEHSU 48CSD2...
Page 34: ...32 MEHSU 18CHF2 MEHSU 24CHF2 MEHSU 36CSF2...
Page 35: ...33 MEHSU 48CSF2 MEHSU 36CSF2 MEHSU 48CSF2...
Page 36: ...34 6 2 Outdoor Unit MCHSU 09PHH2 MCHSU 12PHH2 MCHSU 18PHH2...
Page 37: ...35 MCHSU 24PHH2...
Page 38: ...36 MCHSU 36CSH2...
Page 41: ...39 For MCHSU 48CSH2...
Page 44: ...42 MEHSU 09CHD2 Code 0 Code 1 Code 2 Code 3 Code 4...
Page 45: ...43 MEHSU 12CHD2 Code 0 Code 1 Code 2 Code 3 Code 4...
Page 46: ...44 MEHSU 18CHD2 Code 0 Code 1 Code 2 Code 3 Code 4...
Page 47: ...45 MEHSU 24CHD2 Code 0 Code 1 Code 2 Code 3 Code 4...
Page 48: ...46 MEHSU 36CSD2 Code 0 Code 1 Code 2 Code 3 Code 4...
Page 49: ...47 MEHSU 48CSD2 Code 0 Code 1 Code 2 Code 3 Code 4...
Page 58: ...56 12 Field Wiring 36K 48K...