14
Figure 2
Straight pipes before and after installation
In order to ensure the upstream piping conditions required for high accuracy measurement of the
flowmeter, the piping installation as shown in the figure below is recommended.
According to the position where the electromagnetic flowmeter is installed, when there are valves at the
front and rear, the smallest straight pipe section must meet the installation distance of the first 10D and
the rear 5D, and the valve needs to be fully opened, as shown in Figure 3.
Figure 3
When the plug-in electromagnetic flowmeter is installed at the back end of the T-shaped tube, the
electromagnetic flowmeter and the T-shaped tube need to ensure a straight pipe section of at least 20D
in the front and 10D in the back, as shown in Figure 4.
Figure 4
When the plug-in electromagnetic flowmeter is installed at the near end of the 90° elbow, the
electromagnetic flowmeter and the tail of the elbow need to ensure a straight pipe section of at least the
first 10D and the near 5D, as shown in Figure 5.