mFi Mason-Lite MGFPST-43A Instructions Manual Download Page 13

11

Fireplace Assembly Procedures

1)  Plan  ahead  by  placing  the  hearth  components  (without 

mortar) in the place of the intended installation. Make sure 

the width is 53” and deptch is 28’”. Mark the centers for the 

rebar drill locations. 

2)  a) 

Wood Floor Installations: 

Floor preparation must have been completed as shown in 

page 8 and if Anchor Brackets have been installed 

properly, the protruding threaded rods should line up with 

the rebar holes on the hearth slabs. Mix up a batch of 

mortar and prepare intended underside and joints with a 

1/4” bead, spread out evenly. One half overlaps the other. 

Carefully place hearth slab that is to be overlapped first. 

All-thread rods should stick up through the holes on the 

hearth slab. Complete the overlapping hearth as shown in 

Figure 13. 

  

b) 

Concrete Floor Installations: 

Prepare the surface for Epoxy embedded rebar by drilling 

5/8 inch diameter holes, 4 to 6 inches deep (see Figure 7 

for locations). Thoroughly clean out the holes with 

compressed air or a wire brush prior to the Epoxy process. 

Cut your rebar to the desired length. The rebar included 

with your fireplace is for standard Mason-Lite Fireplace 

opening heights. If a height extension kit is considered, 

you will have to purchase a longer length rebar. 

 

 

Squeeze the epoxy into the hole and firmly push the rebar 

to the desired embedment. (Figure 12). Be sure to 

thoroughly clean out the hole with compressed air or a 

wire bottle brush prior to placing the epoxy. This will 

ensure a sufficient bond to the concrete.

 

 

Figure 12

 

Note* A  DEPUTY  INSPECTOR  MAY  ME  REQUIRED 

FOR THE EPOXY DOWELS PROCESS. CHECK WITH 

YOUR  LOCAL  BUILDING  DEPARTMENT  PRIOR  TO 

REBAR INSTALLATION. 

 

Figure 13

LH Hearth 2nd

RH Hearth 1st

53”

28”

Apply mortar 

between joints

3)  Before installing the side walls, confirm placement of 

outside combustion air side block (if required), this can be 

installed either side depending on which side is accessible 

to outside combustion air. Prepare side wall footprint 

with the prepared mortar. Note: In an island installation, 

outside combustion air is obtained by feeding duct through 

subflooring and then up to supporting structure. 

4)  Keep the assembly of the next sections of the firebox side 

walls moving up, keeping components moist, mixing 

mortar as you need it and threading the mortar 

appropriately as you stack each section, one onto the 

next. Constantly check for squareness and levelness while 

building each course of block. As you complete each 

section, make certain that you adhere the mortar at each 

and every joint. 

 

Figure 14

Setting Firebox Sides

5)  After the last side walls are in place, add #3 rebar rods 

and fill the firebox cells with mortar mix. Mix approx. 2 cu. 

ft. of sanded mortar mix. Put 25% in cells and place #3 

rebar vertically into holes on the hearth base. If a raised 

metal platform was installed, place adjacent to all-thread 

rods sticking through the cells. Make sure the bars are into 

the hearth and at least 1/2” (one-half inch) below top of 

firebox top surface. Finish filling cells. 

 

Installing the Gas Fireplace

Summary of Contents for Mason-Lite MGFPST-43A

Page 1: ...requirements of the ANSI Z21 50 standard Solid fuels shall not be burned in this fireplace This appliance must be vented vertically through the roof This appliance is not for installation in manufactu...

Page 2: ...This page has been left intentionally blank...

Page 3: ...20 500 mm HEARTH EXTENSION BEYOND SIDES 12 300 mm INSULATION FROM FIREBOX 0 0 mm The installation including provisions for combustion ventilation air and required minimum permanent vent opening must...

Page 4: ...NT 2 8 LOWER DOME FRONT 2 9 LOWER DOME SIDE 2 10 UPPER DOME FRONT 2 11 UPPER DOME SIDE 2 12 DOME TOP FOR 12 B VENT 1 13 INSULATION BLANKET NOT INCLUDED 14 12 VENT PLATE ASSEMBLY NOT INCLUDED 15 3 REBA...

Page 5: ...log 30 2 11 MFP 214 Burner Grate Brackets 2 2 Before beginning installation be sure the burner system is complete by comparing its contents with this Parts List Parts may differ depending upon the siz...

Page 6: ...lt in property damage or personal injury 2 3 8 SPILL SWITCH BAFFLE 43 1 4 53 29 5 8 62 1 8 A A GAS INLET 10 1 4 9 3 4 4 1 4 CHIMNEY OR UL 103 12 ID CLASS A SECTION A A CONNECT TO A 12 B VENT B 38 1 4...

Page 7: ...he gas fireplace and its required individual shut off valve must be disconnected from the gas supply piping system while performing any tests of the piping system at pressures in excess of psig The ga...

Page 8: ...plied Model No GML 2 39 44 P A WARNING Any application other than the Intended Use as stated above is in violation of the manufacturer s instructions and is hereby prohibited Such violation may cause...

Page 9: ...radiant heat is maintained to safe limits Combustible Floor Clearances MGFPST43 Mason Lite Fireplaces have been designed with zero clearance to combustible floors Mason Lite Fireplace Chimney System...

Page 10: ...Figure 11 for support of anchor rods by the steel support frames For fireplace support foundations installed on concrete refer to Appendix I and II pages 20 21 for specific instructions Rebar locatio...

Page 11: ...is the task and responsibility of the general contractor installer to see that the proper reinforcement for weight loads are made by a licensed design professional prior to the fireplace installation...

Page 12: ...quately affix all the fireplace components The mortar is premixed and dry and is to be used to adhere all the fireplace components Be sure to use clean water and work it up into a mixture that is past...

Page 13: ...e bottle brush prior to placing the epoxy This will ensure a sufficient bond to the concrete Figure 12 Note A DEPUTY INSPECTOR MAY ME REQUIRED FOR THE EPOXY DOWELS PROCESS CHECK WITH YOUR LOCAL BUILDI...

Page 14: ...till wet 7 Set the remaining lintel as shown in Figure 16 Figure 16 Lintel Lower Dome Side 8 Now you are ready to start the smoke dome assembly Take the lower side dome positioned so that the beveled...

Page 15: ...the framework to house the chimney system Now that you have completed the smoke dome assembly all the components should stack up for a smooth transition into the flue components Setting the smoke dom...

Page 16: ...he finished firebrick floor of the fireplace so that it is at least 11 eleven inches above the combustible floor system Disclaimer Masonry Fireplace Industries wishes to express that as the manufactur...

Page 17: ...hazard MFI cannot be responsible for the make up of material on the exterior of the fireplace you have chosen nor can MFI be held responsible for the materials in a room that may be responding negativ...

Page 18: ...e sections of vertical pipe that are more than 10 ten feet measuring between elbows you must insert at midpoint a chimney stabilizer When installing the stabilizer pull out the support straps with a g...

Page 19: ...n 10 feet the top of the chimney still needs to be at least 2 feet above a point measured from a distance of 10 feet horizontally along the roof Though there are many configurations in meeting these r...

Page 20: ...ht side of the baffle with the sheet metal screws so that the edges are flush with the firebrick Important This baffle assembly and only this the supplied assembly with spill switch must be properly i...

Page 21: ...and all flames main burner and pilot will go out see important note below OPERATING THE BURNER USING THE REMOTE Move the wall switch to the REMOTE position and follow the instructions included in the...

Page 22: ...nd chimney system must be completely dry This means that the unit must stand without any firing for a minimum of 28 days Only after that period of time can a first lighting take place Do not let the f...

Page 23: ...done twice a year In colder climates cleaning should be done more often Always allow the fireplace to completely cool before you work on it which means of course shutting off all gas and electrical c...

Page 24: ...lts a Check with a millivolt meter Should be 250 millivolts or more b Pilot flame making a blowing sound b Pilot needs adjusting see Checking and Adjusting the Pilot on page 22 c Generator wire leads...

Page 25: ...ncrete slab The concrete strength and durability shall comply with Sections 1903 1904 and 1905 of the International Building Code IBC TABLE R402 2 MINIMUM SPECIFIED COMPRESSIVE STRENGTH OF CONCRETE MI...

Page 26: ...ly b Lines defining areas are approximate only Local conditions may be more or less severe than indicated by region classification A severe classification is where weather conditions result in signifi...

Page 27: ...liate thereof liable in any respect for any injury or damage to the building or structure in which the fireplace has been installed or to the persons or property therein arising out of the use misuse...

Reviews: