Adjust the drawbar at 15-22” above the ground.
Extend or shorten the drawbar so horizontal distance
from end of tractor PTO shaft to center of hitch pin
hole is 14” for 540 RPM 1-3/8-6 spline, (16” for
optional 1000 RPM 1-3/8-21, 20” for 1000 RPM 1 3/4-
20 spline). Secure the drawbar so the hitch pin hole is
located directly below the PTO drive line. PTO
adapters are not recommended as damage to the
drive line may occur. A hitch pin with a minimum
diameter of 1” and bottom retaining pin is
recommended.
AN IMPROPERLY LOCATED HITCH POINT MAY
CAUSE DAMAGE TO THE UNIVERSAL JOINTS OF
THE PTO DRIVE SHAFT. CONFORMING TO THE
DRAWBAR AND PTO RELATIONSHIP SHOWN ON
FIGURE 1, PAGE
WILL ENSURE THAT THE PTO
DRIVE SHAFT WILL NOT BECOME OVER
EXTENDED. USE THE CORRECT SETTING FOR
14” - 540 RPM 1 3/8-6 or 16” - 1000 RPM 1 3/8-21,
or 20” - 1000 RPM 1 3/4- 20. WITH INITIAL HOOK-
UP TO YOUR NEW MEYER SPREADER TEST PTO
TRAVEL BY TURNING EQUIPMENT IN BOTH
DIRECTIONS OBSERVING THE MINIMUM AND
MAXIMUM TRAVEL DIMENSIONS AS SHOWN PER
DRAWING ON FIGURE 7, PAGE
PTO LUBRICATION
LUBRICATION
A high quality Lithium Base Grease should be used.
PRIOR TO USE
NORMAL OPERATION
FAILURE TO FREQUENTLY GREASE THE CV
CENTER
HOUSING
AND
TELESCOPING
MEMBERS WILL REDUCE THE LIFE OF THE CV.
MAINTENANCE INFORMATION
It is extremely important to follow the maintenance
guidelines. If telescoping members become hard to
slide during normal operation, it is recommended the
shaft be taken apart, cleaned with solvent and re-
coated with grease before re-assembling. As a
minimum it is important this be done after each
season of use.
A.
Using the CV Zerk (Key #2) place 20 pumps of
grease into the CV center housing. This should be
done with the drive line / CV as straight as possible.
B.
Slowly articulate the double joint through its
maximum joint angle several times.
C. Return the CV joint to its straight position and insert
additional grease into the CV Zerk (Key #2) until
grease is evident around the housing and center
sliding disk.
A.
Lubricate the following items after every eight
(8) hours of operation. If short rows and frequent
turning or other demanding conditions exist,
lubricate at four (4) hour intervals.
1. Cross and bearings (Key #1)-Add grease until it
is purged around the seals.
2. CV center housing (Key #2)-Add grease until it is
evident around the center sliding disk. (Grease
fitting on CV-some models only)
3. Telescoping members (Key #3)-Add grease until
it adequately covers the sliding members. Take
apart occasionally to make sure adequate
lubrication is being added.
4. Shield bearings (Key #4)-Add 2-3 pumps.
5. Over-running clutch (Key #5) Add 10 pumps
every 25-30 loads.
FIGURE 8. PTO DRIVE LINE
IMPORTANT: GREASE 2 FITTINGS DAILY
Summary of Contents for V-FORCE 7400 Series
Page 30: ...PB 74 7500 30 REPAIR PARTS FRONT SHIELD SIDE SHAFT DRIVE...
Page 32: ...PB 74 7500 32 AUGER DRIVE PRIMARY REDUCTION...
Page 35: ...PB 74 7500 35 This Page Intentionally Blank...
Page 40: ...PB 74 7500 40 BOX AUGERS SIDE SHAFT...
Page 42: ...PB 74 7500 42 7400 7500 UNLOADING GATE MATERIAL GUIDES 7500 PRIOR TO 2011 MODEL YEAR...
Page 44: ...PB 74 7500 44 7400 7500 UNLOADING GATE MATERIAL GUIDES CONT D 7500 PRIOR TO 2011 MODEL YEAR...
Page 46: ...PB 74 7500 46 7500 UNLOADING GATE MATERIAL GUIDES 2011 MODEL YEAR LATER...
Page 48: ...PB 74 7500 48 SPINNERS GEARBOX SHAFT DRIVE...
Page 53: ...PB 74 7500 53 This Page Intentionally Blank...
Page 54: ...PB 74 7500 54 HUBS AXLE TANDEM AXLE ASSEMBLY...
Page 56: ...PB 74 7500 56 THIRD AUGER...
Page 58: ...PB 74 7500 58 OIL KIT...
Page 60: ...PB 74 7500 60 V FORCE LIGHTING...
Page 71: ...PB 74 7500 71 This Page Intentionally Blank...
Page 75: ...PB 74 7500 75 This Page Intentionally Blank...
Page 84: ...PB 74 7500 84 This Page Intentionally Blank...
Page 85: ...NOTES...
Page 86: ...NOTES...