METAL CONDUCTS ELECTRICITY:  

Do not use this equipment where contact may be made with power lines or other live electrical circuits.

FAILURE TO UNDERSTAND AND FOLLOW ALL SAFETY RULES AND ASSEMBLY INSTRUCTIONS COULD 

RESULT IN SERIOUS INJURY OR DEATH.

READ BEFORE BEGINNING ASSEMBLY.

DO NOT OVERLOAD:  

Scaffolding maximum load: 800 lb (363 kg). Platform: 25 lb/sq. ft. (122 kg/m

2

)

ASSEMBLY PROCESS

1. Preparation

•  Locate the tower, ensuring ground is level.
•  Unlock the interlock pins on all frames.
•  When installed, always move the interlock pin to the 

“locked” position.

•  Sort the braces into horizontal and diagonal braces 

the diagonals are slightly longer.

•  Unlock the brace locks.

Note the locking and unlocking position for 
the casters.

2. Base

Step 1:  Ensure interlock pins are removed from the base frame.
Step 2:  Install caster frames (bottom frames).
Step 3:  Insert the interlock pin as shown.
Step 4:  Lock casters before ascending any part of the tower

3. Locking down the platform (Windlock)

A windlock clip is installed on the platform at the hook.  

This is locked as shown here.

Summary of Contents for AL-Q0108

Page 1: ...FORE USING THIS PRODUCT KEEP THIS MANUAL HANDY FOR FUTURE REFERENCE 1 800 363 7587 Customer Service Picture may differ from actual product MODEL AL Q0108 IN Q0108 US 01 OPERATIONAL SAFETY AND ASSEMBLY INSTRUCTIONS EASY SET SCAFFOLD TOWER ...

Page 2: ... ground is level Unlock the interlock pins on all frames When installed always move the interlock pin to the locked position Sort the braces into horizontal and diagonal braces the diagonals are slightly longer Unlock the brace locks Note the locking and unlocking position for the casters 2 Base Step 1 Ensure interlock pins are removed from the base frame Step 2 Install caster frames bottom frames...

Page 3: ... contact your distributor to get extra components Do not lift or suspend an assembled mobile tower Damaged components or components from other tower systems must never be used Stabilisers should always be fitted when specified Use the stabiliser shown in the component list according to the tower height When wind exceeds Beaufort s force 4 cease using the tower If wind is expected to reach Beaufort...

Page 4: ... the stabilisers so that the footpads are approximately equidistant from each other as shown in Fig 2 Adjust the outrigger and reposition the clamps as required to make firm contact with the ground Ensure the clips with locking pin are in place When in the correct position tighten the clamps firmly To position the tower against a wall do not remove the stabiliser move parallel with the wall Fig 3 ...

Page 5: ...5 15 TRADE TOWER 7 1m 1 2 3 4 5 7 6 8 INSTRUCTIONS x6 ...

Page 6: ...6 16 TRADE TOWER 7 1m 9 13 10 14 11 15 12 16 ...

Page 7: ...7 17 TRADE TOWER 7 1m 17 21 18 22 19 23 24 20 ...

Page 8: ...8 18 TRADE TOWER 7 1m 25 29 26 27 28 Metaltech is a registered trademark of Metaltech Omega inc WWW METALTECH CO 1 800 363 7587 LAVAL QUEBEC CANADA H7L 3N6 ...

Reviews: