Before setting up and connecting the boiler, it is necessary to check that all components 
are operational and that the boiler is fully equipped for operation. 

 4.3. Installation of the boiler in the boiler room 

The boiler doesn't need a foundation. It is placed directly on the floor. It should be exactly 

levelled! The strength of the floor as well as fire protection     conditions must be taken into account. 
Installation of the boiler should take into account the possibility of free cleaning of the boiler and 
access  to  its  every  part.  The  room  where  the  boiler  is  installed  should  have  two  gravitational 
ventilation  openings,  min.  15  x  15  cm  (applies  to  small  boilers,  for  larger  ones,  the  ventilation 
system  should  be  recalculated  by  an  authorized  person,  one  at  the  boiler  room  floor  and  one 
under  the  ceiling.  Holes  should  be  secured  with  steel  mesh.  Do  not  cover  boiler  ventilation 
openings, do not use empty spaces in the boiler casing for waste storage, etc. 

 

The use of mechanical exhaust ventilation in the boiler room is prohibited. 

 

It is permissible to use the above mentioned exhaust system under the condition that a 

mechanical  supply  system  with  the  capacity  compensating  for  the  amount  of  exhaust  air  is 
installed in accordance with PN-87\B-02411.  

Room of the boiler room 

The room in which the boiler is installed must not be intended for permanent or temporary 

residence of people. In new buildings, the minimum room height is 2.2 m and in existing buildings 
1.9 m. The boiler must be placed on a non-flammable surface. The boiler must be positioned so 
as to ensure trouble-free operation, cleaning and maintenance.  

 

Ventilation 

In boiler plants up to 25 kW, the supply air ventilation should be carried out by means of 

an unclosed opening of at least 200 cm2, while the exhaust air should be in the form of an exhaust 
grille of at least 14 x 14 cm.  
In boiler plants with power outputs from 25-2000 kW, there should be an air supply duct with a 

cross-section of not less than 50% of the chimney section area, but nevertheless less than 20x20 
cm. The outlet should be up to 1 m above floor level. The boiler room should also have an exhaust 
duct of not less than 25% of the chimney section area with an inlet opening under the boiler room 
ceiling, led above the roof and placed, if possible, next to the chimney. The minimum dimensions 
of the chimney section are 15x15 cm.  

 

 Heating installation - boiler installation 

The feeder can be assembled to the boiler by persons with the appropriate permissions, 

who have familiarized themselves with the technical and operating documentation of the feeder. 
It is the user's responsibility to ensure that the installation of the boiler is carried out in accordance 
with the applicable regulations. The assembling company should issue a guarantee for the works 
performed and confirm their execution with the installation protocol attached to this manual. 
The  customer  should  have  a  statement  from  the  chimney  sweep  regarding  the  passage  and 

draught of the flue to which the boiler will be connected.  

 The  boiler  must  be  levelled  and  positioned  so  that  the  connection  to  the  boiler  is  tight.  Boiler 

equipment includes a set of temperature sensors.  

Boiler operation in adverse weather conditions 

In  case  of  unfavourable  conditions  for  chimney  draught  or  unfavourable  weather 

conditions,  it  is  necessary  to  make  sure  that  the  chimney  is  unobstructed.  If  there  is  no  other 

Summary of Contents for GHT

Page 1: ...GHT Operation and maintenance documentation Transtlation of the original manual Issue I 05 05 2020 ENGLISH...

Page 2: ...maintenance during its lifetime The manufacturer is not responsible for any damage resulting from improper connection installation and use of the device It is forbidden to touch and disassemble the p...

Page 3: ...ing the boiler to central heating systems 20 5 1 installation of the boiler in an open system 21 5 2 installation of the boiler in a closed system 21 6 Operation and use of the boiler 23 6 1 basics of...

Page 4: ...the boiler is a company METAL FACH Heating Technology Jacek Kucharewicz Information and pictograms The following information pictograms have been used to mark dangerous places on the device These oper...

Page 5: ...of chimneys which do not comply with building standards Failure to perform basic periodic cleaning and maintenance of the boiler Mechanical damage Following the recommendations and advice given in thi...

Page 6: ...p new installations repeated check every 2 years Tightening of the dust emission limit values 20 mg m and CO 400 mg m in 1st degree BImSchV regulation 2 After the transition period the emission limits...

Page 7: ...ling of the system during this period must be carried out with hot water so that the water in the system does not freeze during filling CAUTION If there is any suspicion of the possibility of water fr...

Page 8: ...ndations and instructions We recommend it All persons must have access to the operating instructions and must be familiar with them and comply with their instructions before starting to operate the de...

Page 9: ...lation doors connection spigots clean hatch covers and control unit feeder and fuel tank Installation of the boiler unit in a household level boiler room is recommended under the supervision of an aut...

Page 10: ...atch is the basic amount that affects the combustion It determines the energy efficiency and thus the potential energy yield during combustion The calorific value of wood based fuels ranges in practic...

Page 11: ...umidity is 100 u 100 Determination of fuel requirements From the calorific value and the required rated thermal output you can calculate the fuel requirement Important factors influencing this paramet...

Page 12: ...can be max 30 M30 Bulk density of wood chips depending on water content according to EN ISO 17225 4 Quality characteristics of wood chips Good quality wood chips low homogeneous water content without...

Page 13: ...it falls to the bottom Poor quality wood pellets cracked rough surface large length differences high dust content floats 1 4 4 Minimum fuel requirements Ingredients When buying wood for combustion ch...

Page 14: ...are designed for preparation of hot water in central heating systems to the temperature at the boiler outlet not exceeding 95 oC They can be used in central heating and domestic hot water systems bot...

Page 15: ...m It is used for emergency extinguishing of the firebox Under the combustion chamber there is an ashtray Periodic cleaning of the boiler exhaust system takes place through the inspection openings plac...

Page 16: ...entral heating Fig 4 Basic overall dimensions of the boiler side rear view 1 fuel tank filling flap 2 the controller control panel 3 cleaning door 4 the firebox door 5 ashtray door Internal water refi...

Page 17: ...17 Drawing 5 Detailed dimensions of the 22 kW Drawing 6 Detailed boiler dimensions 40 kW Drawing 7 Electrical diagram of the GHT 22 kW boiler Drawing 8 electrical diagram of GHT 40 kW boiler...

Page 18: ...ntilation and flue gas discharge Water for supplying boilers and heating installations must be free of mechanical impurities and should be characterised by parameters in accordance with the PN 85 C 04...

Page 19: ...er must be transported in vertical position Otherwise the steel jacket of the boiler insulation may be damaged The boiler is delivered in an assembled condition To make it easier to bring the boiler t...

Page 20: ...aning and maintenance Ventilation In boiler plants up to 25 kW the supply air ventilation should be carried out by means of an unclosed opening of at least 200 cm2 while the exhaust air should be in t...

Page 21: ...used to calculate the chimney section area 0 003 x Q x 0 86 F m h where Q is the heat output of one or more boilers connected to one flue pipe kW h height of the chimney measured from the level of th...

Page 22: ...with a capacity of min 4 7 of the total volume of central heating installation safety pipe with a diameter depending on the heat output of the boiler Collecting signalling bypassing and venting pipe a...

Page 23: ...stallation model in houses supplied with water through a hydrophore and in places exposed to frequent interruptions in water supply In such cases it is not necessary to install the boiler in a closed...

Page 24: ...e boiler controller fig 16 Controller The temperature controller regulator is a device which allows you to control the operation of the feeder and the blowing fan Additionally the device can cooperate...

Page 25: ...needed for automatic operation of the feeder In the case of a lower level dust from the tank may occur To do this it must be ensured that the tank is always filled above the minimum level to ensure c...

Page 26: ...embers to move back to the tank and pouring water into the combustion chamber 2 2 remove the fuel from the combustion chamber into a drawer or tin container taking care not to burn use short periods o...

Page 27: ...abnormal chimney draught unclosed boiler door picture 13 install a chimney draught regulator improve draught close the stove door 2 Suspension of fuel in the tank use of fuel with a dust content of mo...

Page 28: ...10 Boiler does not reach the set operating temperature use of the wrong fuel fuel with too high a humidity above 30 dirty combustion chamber obstructed head ventilation openings inappropriate controll...

Page 29: ...ystem safety valve firefighter 3 Feed flap spring 4 Piston blind spot sensor Hall sensor 5 Igniter 6 Feeding mechanism ties 7 Burner WARNING the above mentioned parts are not subject to warranty repla...

Page 30: ...p Wrong Picture 3 Firebox inspection flap GOOD Photo 4 Example of a controller Picture 5 Fuses Picture 6 Protective plate Picture 7 Fuel tank Picture 8 Chimney flue Picture 9 Tray lid with locking mec...

Page 31: ...htray door closed properly Picture 14 Ceramic cartridges catalysts Picture 15 2 m3 palletized woodchip Photo 16 Example of a furnace controller Picture 17 Example of a room controller Photo 18 chips f...

Page 32: ...METAL FACH...

Reviews: