Pre drill 

hole

30mm 

screw

IMPORTANT : 

Pre-drill before fixing screws.

1

7

Step 17

Parts Needed - No. 1 QTY 1

 

 

   No. 7 QTY 2

Place the window 

(No. 1)

 onto a flat 

surface and fix 2xT-hinges 

(No. 7) 

to the 

window using 3x30mm black screws per 

hinge.

  

Locate the window into the window 

frame on the cabin, ensuring there is 

equal spacing on each side between the 

window and window frame.

Secure into position by screwing 

through  the T-hinges 

(No. 7)

 using 

5x30mm black screws per hinge. 

*Ensure to screw into the framing and 

not into the channel.

 

Use this method to assemble 2 windows. 

32x30mm Black Screws

8

Pre drill 

hole

30mm 

screw

8

Step 18

Parts Needed - No. 8 Qty 1

Fix the casement stay 

(No. 8)

 onto the 

window 

(No. 1)

 and the casement stay pins 

to the window framing using 6x30mm 

black screws.

*Ensure the casement stay is  centralised 

on the window.

Use this method to fit one casement stay to 

each window. 

12x30mm Black Screws

IMPORTANT : 

Pre-drill before fixing screws.

IMPORTANT : 

Pre-drill before fixing screws.

Pre drill 

hole

30mm 

screw

9

10

17

Step 19

Parts Needed - No. 9 QTY 1

 

 

   No. 10 QTY 1

 

 

   No. 17 QTY 6

Once the roof is fixed, 

place the master 

and secondary doors 

(No’s 9 & 10)

 onto 

a flat surface and fix 3x9 inch T-hinges 

(No.17) 

to each door using 5x30mm 

black screws per hinge.

  

Locate the doors into the door frame on 

the cabin, ensuring there is equal 

spacing on each side between the doors 

and door frame.

Secure into position by screwing 

through  the T-hinges 

(No.17)

 using 

4x30mm black screws per hinge, 

 

making sure the doors open & close 

freely without restriction 

*Ensure to screw into the framing and 

not into the channel.

 

54x30mm Black Screws

Summary of Contents for 0619PNNE0324HGDD2SW-V1

Page 1: ...rm sunshine and sheltered as much as possible during rain or snow BUILDING A BASE When thinking about where the building and base are going to be constructed Ensure that there will be access 60cm to a...

Page 2: ...71x70x805mm Qty 2 AI 0619LOGSWBF V3 7 6 Inch T Hinge QTY 4 PI 07 0113 8 Casement Stay Qty 2 PI 07 0008 Double Door Contents 10 9 11 12 Mortice Lock Qty 1 PI 07 0017 Key Plate Qty 1 Handles Pair Qty 1...

Page 3: ...oof Spacers QTY 5 PI 07 0208 20x100x2mm 43 Log Board 120x19x2396mm QTY 25 LB19 A 2396 Finisher Board 54x19x2996mm QTY 1 LB19RG54 A 2996 Finisher Board 97x19x2996mm QTY 1 LB19RG97 A 2996 Log Board 120x...

Page 4: ...n total ensuring the bearers are flush Once fully assembled ensure the bearers are square by measuring from corner to corner as illustrated making sure the measurements are equal If the bearers are no...

Page 5: ...nd fix the starter boards in place Fix each of the starter boards to the frame by screwing through the notch into the frame as shown in the illustration 4x70mm Screws 24 26 25 26 26 29 27 Step 4 Parts...

Page 6: ...he door section slide the assembled door frame over the boards resting the frame on top of the starter board if you have not yet assembled the door frame refer to step 5 Please note This image is for...

Page 7: ...second level of boards onto the log cabin slide the windows between the smaller boards and rest on to the longer board if you have not yet assembled the window frames refer to step 8 Ensure the board...

Page 8: ...be required to fit parts 70mm screw Pre drill hole 34 22 25 22 Step 12 Parts Needed No 22 QTY 2 No 25 QTY 1 No 34 QTY 1 Following the method shown in the illustration place the bottom gable No 22 the...

Page 9: ...using 1x70mm screw per corner Ensure to stagger the screws so as not to collide with the previous screw 4x70mm Screws 23a Rubber Mallet may be required to fit parts 23b 23b 23a 35 35 Pre drill hole 7...

Page 10: ...longer than the log boards by 2mm each end You have been issued with 23 roof boards but in reality you may only need to use 22 The last roof board will overhang past the end of the roof purlin Using...

Page 11: ...8 onto the window No 1 and the casement stay pins to the window framing using 6x30mm black screws Ensure the casement stay is centralised on the window Use this method to fit one casement stay to each...

Page 12: ...is for illustrative purposes and may differ from your choice in product regarding ironmongery Nevertheless the process of fixing the frames is the same 8x30mm Black Screws 4x30mm Screws a b 30mm scre...

Page 13: ...h of the floor boards into the floor bearers 156x40mm Screws IMPORTANT Pre drill before fixing screws Closure Trim Internal 23 Measure and cut the closure trims to fit the internal space Closure Trim...

Page 14: ...vals Felt size 3200mm L X 1000mm W 110x Felt Tacks 1 2 3 45 40mm screw Pre drill hole 38 39 38 Step 26 Parts Needed No 38 QTY 2 No 39 QTY 2 Attach the fascia s No 38 39 around the building ensuring to...

Page 15: ...e Winter and shrink during periods of low moisture Summer Storm braces will help your building expand and contract properly Important Ensure each bolt is tightened using a washer so as not to damage t...