![Mercia Garden Products 01OVLPRA0604SDFW-V1 General Instructions Manual Download Page 4](http://html1.mh-extra.com/html/mercia-garden-products/01ovlpra0604sdfw-v1/01ovlpra0604sdfw-v1_general-instructions-manual_1772639004.webp)
P 19
Please retain product label and instructions for future reference
Step 5
i)Position a truss frame to the
ridge bar sloping down towards
the building side, ensure it is
central to the ridge bar. Fix with a
50mm screw through the ridge
bar into the truss frame.
ii) Align the second truss frame
with the first on the opposite side
of the ridge bar and fix with a
50mm screw at an angle as
illustrated.
ENSURE SUPPORT BARS
ARE MANUALLY SUP-
PORTED UNTIL FIXED AT
BOTH ENDS
i
ii
4x50mm Screws
Pre drill
hole
50mm
screw
9
9
Step 6
Fix a panel block on both sides of
the building positioned central to
the truss frame and flush with the
underneath of the panels fram-
ing. Screw through the ouside of
the building through the clad-
ding into the panel block using 2x
30mm screw per block.
4x30mm Screws
Pre drill
hole
14
14
14
30mm
screw
Step 7
i) Fix the truss block to the side
panel block with 2 x 50mm
screws. Position the block at the
top of the framing with the
angle pointing upwards into the
building, aligning the block
centrally along the join between
the side panels with one screw
in each panel.
ii) Fix the truss frame to the
block using 1 x 50mm screw.
ii
i
11
6x50mm Screws
Pre drill
hole
50mm
screw
11
Step 8
Fix a Truss support
between the two truss
frames and fix in place
using 40mm screws,
ensure you pre-drill
holes before fixing
together.
4x40mm Screws
40mm
screw
Pre drill
hole
10