P 18
Please retain product label and instructions for future reference
Step 1
4
4
12x30mm Screws
Place floor on firm and level base, ensure
base has suitable drainage free from areas
where water can collect. (See front page on
base requirements).
Attach the floors using 12 x 30mm screws
30mm
screw
Pre drill
hole
Do not secure the building to the
floor until the roof is fitted.
Fix the corners with 50mm screws
as shown in diagram.
Position the panels so there is equal spacing
between the floor and cladding on all 4 sides
Step 2
2
3
7x50mm Screws
Pre drill
hole
50mm
screw
6
Step 3
13x50mm Screws
Fix the corners with 50mm
screws as shown in diagram.
Pre drill
hole
50mm
screw
1
3
6
Step 4
24
8
8
22
22
Ridge Bar Assembly
Position the two parts of the
ridge bar within the ‘U’
channel and secure from
either side with 3 x 30mm
screws and 4 x 30mm screws
from underneath. Secure an
‘L’ bracket to either end of
the ridge bar using 2 x
30mm screws per bracket.
18x30mm Screws
Place the roof support bar
in between the front and
back panels. Ensure the top
corners of the support bar
are flush with each top
point. Secure in place using
the L Bracket on each end
with 4x30mm screws.
30mm
screw
Pre drill
hole