Target group
Trained electrician wearing PPE for installation[2.2 Personal protective equipment (PPE); S.8]
Tools required
13 open-ended spanner
Screwdriver(6.5 mmslot,insulated)
Screwdriver (TX 20)
Hexkey(4 mmand3 mm)
Before dismantling the Mercedes-Benz Energy Storage Home it must be switched off
[6.1 Switching off; S.21].
(1) Remove the Hv cables and RJ45 cable from the inverter.
Follow the installation instructions for the Sunny Island inverter connected.
(2) Remove the RJ45 cable from the system cover.
(3) Unscrew and remove all trunking covers.
(4) Remove the two expanding rivets and take off the system cover.
(5) Remove the two lower expanding rivets and remove the base cover (wall assembly).
(6) Unplug the RJ45 terminating resistor.
(7) Unplug all Hv cables from the positive and negative terminals and remove them.
(8) Unplug all protective earth and remove them.
(9) Remove the nuts from the installation rails.
(10) Remove the energy storage modules from the installation rails.
(11) Unscrew and remove the wall fastening screws.
(12) Remove the installation rails from the base (upright installation).
•Mercedes-BenzEnergyStorageHomeisnowdismantled.
After dismantling energy storage modules, make sure you store them correctly [9. Storage; S.22]
6.1 Switching off
(1) Switch off the Inverter.
(2) Switch off the Mercedes-Benz Energy Storage Home using the oN/oFF switch.
(3) Wait 30 seconds.
•Thesystemhasnowbeenshutdown.
Apply the following procedure when starting up your
Mercedes-Benz Energy Storage Home.
Take note of the installation instructions for the
inverter used.
6.2 Dismantling
21
Mercedes-Benz Energy Storage Home Manual
| Starting up | Dismantling
Summary of Contents for Energy Storage Home
Page 1: ...Mercedes Benz Energy Storage Home Manual...
Page 2: ......
Page 26: ...Your notes 26...
Page 27: ......