28
OM 200MICRO
Menu 15, Schedule
Item
Screen
Line
Display
Field
Range
Extended Name
Override=00.0Hr
1
00.00-63.75
Manual Schedule Override
1
Network Sched=
2
1-32
Network Time Schedule
Sun 00:00-23:59
1
00:00-23:59
Sunday Run Schedule
2
Tue 00:00-23:59
2
00:00-23:59
Tuesday Run Schedule
Mon 00:00-23:59
1
00:00-23:59
Monday Run Schedule
1
3
Wed 00:00-23:59
2
00:00-23:59
Wednesday Run Schedule
Thu 00:00-23:59
1
00:00-23:59
Thursday Run Schedule
1
Sat 00:00-23:59
2
00:00-23:59
Saturday Run Schedule
Fri 00:00-23:59
1
00:00-23:59
Friday Run Schedule
2
Hol 00:00-23:59
2
00:00-23:59
Holiday Run Schedule
1
Jan-Dec
2
00-31
2
3
One Event N/A-00:00-23:59
3
00:00-23:59
Time Schedule Override
0verride=
This allows the operator (manual input) to input a time value that the MicroTech will ignore
the normal or holiday start/stop schedule. This timed override will start when the value is entered.
Network Sched=
Network schedules can be provided through a network master panel when the
Mode
(menu 11)
is set to
auto:network
. If a master/slave arrangement is active, the master panel will control
the schedule. The slave unit should be programmed the same as the master to have consistent
operation should the network communications fail.
Sun thru Fri
—The start time
(first value)
and stop time for each day of the week should be entered.
The default value (00:00-23:59) allows the chiller to operate continuously.
Hol
—The time entered at this menu will control the chiller nun time for the holiday dates entered in
menu 16
(holiday date).
One Event
—This is a one time schedule which will allow the chiller to operate on the month, day and
time specified. This allows a special override time to be set in advance instead of using the
Override
as described above.
Press the "NEXT MENU" key and menu 16
(Holiday Date)
will be displayed. Menu 16 has three
screens. This menu is password protected and requires the operator password. Screen one has 1-6,
screen two has 7-12 and screen three has 13-14 holiday dates. The first screen is shown for
description purposes. The month, day and number of days in the holiday is selected. The start and
stop time was selected in menu 15
(Schedule).
Menu 16, Holiday Date
Item
Screen
Line
Display
Field
Range
Extended Name
1
Jan-Dec
Holiday Month
2
00-31
Holiday Date
#1=N/A-00 00 Day(s)
3
00-31
Duration Days
1
Jan-Dec
Holiday Month
2
00-31
Holiday Date
1
#4=N/A-00 00 Day(s)
3
00-31
Duration Days
1
Jan-Dec
Holiday Month
2
00-31
Holiday Date
#2=N/A-00 00 Day(s)
3
00-31
Duration Days
1
Jan-Dec
Holiday Month
2
00-31
Holiday Date
2
#5=N/A-00 00 Day(s)
3
00-31
Duration Days
1
Jan-Dec
Holiday Month
2
00-31
Holiday Date
#3=N/A-00 00 Day(s)
3
00-31
Duration Days
1
Jan-Dec
Holiday Month
2
00-31
Holiday Date
1
3
#6=N/A-00 00 Day(s)
3
00-31
Duration Days
Table Continued