Installation
5.3
Trial operation
1. Put the conveyor system into operation and let it run for at least
10 minutes. After operation, switch it off and disconnect the
power supply.
2. Check all screw connections. If required, re-tighten them.
3. If necessary, adjust the tracker at the main front surface (1, Fig.
26) to the correct conveyor belt guide.
4. Loosen the set screws (2, Fig. 26), which secure the telescopic
pipe (3, Fig. 26).
5. Move the main front surface (1, Fig. 26) as much as possible in
the direction in which the conveyor belt is meant to be moved.
6. Tighten the set screws again (2, Fig. 26).
7. If the wear and tear or bulk material accumulation is excessive
or other problems occur, refer to the information in chapter 5.4
"Installation check-list" or chapter 7 "Troubleshooting".
NOTE
Read through this chapter thoroughly before starting any work on
the belt centring system or the customer's conveyor system.
CAUTION! FLYING PARTS!
Tools or installation parts which are left behind can fall from a
moving conveyor belt and may cause minor injuries and damage
to property.
After installation, first remove the tools from the place of installa-
tion and from the conveyor belt before switching on the power sup-
ply.
WARNING! DANGER OF INJURY!
Body parts and/or clothing may get caught and pulled in by rotat-
ing parts or by the moving conveyor belt.
Before any installation or maintenance work is carried out, ensure
that all power sources to the conveyor belt system and its acces-
sories are switched off and secured against inadvertent reactiva-
tion.
Use warning signs!