background image

LOOSE LAID

The most critical requirement when loose laying a one piece 

Insight

®

 Plus GB

 installation is to be certain that the material is 

laying flat and positioned squarely in the room. In long drops, pull a string down a pattern line to assure that the material is 

positioned squarely in the work area. 

Provide a gap of between 1/8”to 1/4” around all edges of the 

Insight

®

 Plus GB

 flooring. Undercut all of the material. Once 

the 

Insight

®

 Plus GB

 is positioned in the room, allow 15 to 20 minutes for the material to relax and lay flat before the final 

trimming. Undercut all door casings so the material can be slid under these casings without “pinching” or locking material. 

When fitting around in-floor forced air vents it may be nessacery to apply a narrow band of adhesive around the vent to 

prevent air from being blown under the flooring. 

Never secure cabinets or other permanent fixtures on top of loose laid 

Insight

®

 Plus GB

. Be certain that wall base and 

transition strips are not fastened into 

Insight

®

 Plus GB

SEAMED INSTALLATION

When the work area requires more than one drop of 

Insight

®

 Plus GB

, determine the best possible placement of the seam. 

If the work area requires more than one seam the Fully Adhered (either Permanent Bond or Releasable Bond) method must be 

used. Fit and cut the first sheet as in a one piece installation. Weight this sheet to prevent it from shifting. Position the second 

sheet in the room and align it to the first sheet for accurate pattern match. Once you have achieved pattern alignment, weight 

the second sheet to prevent it from shifting.

PATTERN MATCHING

When your work area requires more than one sheet of material, provide additional length on the second and succeeding 

sheets to allow for proper pattern alignment. Install 

Insight

®

 Plus GB

 using the “Reverse” or “Do Not Reverse” method. 

The printed directional arrows on the backing of the 

Insight

®

 Plus GB

 can be helpful in determining the direction of sheet or 

fill piece if needed.

“REVERSE” METHOD

“Reverse Sheets for Seaming” means turning the second sheet 180° to the first sheet.  To determine the amount of additional 

material required to assure proper pattern alignment when the “Reverse” method is recommended, cut the first sheet at least 

3" longer than the net room requirements. Cut the second and all succeeding sheets to this length plus the length of the 

pattern repeat.

“DO NOT REVERSE” METHOD

“Do Not Reverse Sheets for Seaming” means placing the opposite selvage edges together.  To determine the amount of 

additional material needed to align patterns in “Do Not Reverse” designs, cut the first sheet 3" longer than the net room 

requirements. Cut the second and all succeeding sheets to the next multiple of the pattern repeat over the net room 

dimension, providing the starting wall is the same.

SEAM CUTTING

Seaming is one of the most important aspects of resilient sheet installation. Always double-cut seams in Mannington 

Insight

®

 

Plus GB

 with a new, sharp utility knife blade.

DOUBLE-CUTTING OF SEAMS

The most accurate method for cutting seams in 

Insight

®

 Plus GB

 is double-cutting. In this technique, both sheets are cut at the 

same time. This ensures the edges of both sheets are cut exactly the same, with no gaps or fullness. The construction of 

Insight

®

 Plus GB

 will not permit the product to be compressed or  stretched  into  match. Overlap the sheets of 

Insight

®

 Plus 

GB

 and bring the pattern into an exact match. The most accurate method of maintaining the pattern grout line width is to 

make the seam cut along the side of the grout line. With the sheets aligned, position the steel straightedge so it completely 

covers the grout line of the top sheet. Using the straightedge as a guide, cut the length of the seam in the “shadow” of the 

grout line with a utility knife. This technique will ensure that all grout lines are of the same width. 

Choices that Work.

Questions about warranties? call 800 241 2262 or visit www.manningtoncommercial.com 

July, 2015 

Insight

®

 Plus GB

Installation Guidelines

Insight

®

 Plus GB Instal

lat

ion Guidel

ines

Summary of Contents for Insight Plus GB

Page 1: ...materials for subfloor preparation MATERIAL RECEIVING HANDLING STORAGE 1 Always store Insight Plus GB tightly rolled face out on a sturdy cardboard core designed for that purpose Store the roll horizo...

Page 2: ...can Corp 757 425 1206 www koesterusa com Mapei 800 426 2734 www mapei com Uzin Ltd 800 505 4810 www ufloorsystems com SUBFLOOR PREPARATION Concrete Careful subfloor preparation is vital for an excelle...

Page 3: ...ess Have a written warranty for suitability and performance from the panel manufacturer or have a history of proven performance e Any unevenness at the joints between panels must be sanded to a level...

Page 4: ...placing the Insight Plus GB into the wet tacky MT 711 adhesive with a 1 16 x1 32 x1 32 notched trowel the substrate must be smooth and have sufficient porosity to receive the adhesive For wood substr...

Page 5: ...o the adhesive to eliminate trapping air Do not drop or flop the material into the adhesive Using a 50 lb or heavier three section floor roller roll the material in both directions starting in the mid...

Page 6: ...n determining the direction of sheet or fill piece if needed REVERSE METHOD Reverse Sheets for Seaming means turning the second sheet 180 to the first sheet To determine the amount of additional mater...

Page 7: ...ong the length of the seam You must apply seam sealer into the seam cut and leave a bead of sealer approximately 1 8 wide centered on the seam Remember it is crucial that the seam sealer be applied to...

Page 8: ...deep If the Insight Plus GB was installed FULLY ADHERED apply a thin layer of MT 711 to the back of the repair piece and place into position Roll with a hand roller Apply MLG 33 seam sealer Protect f...

Reviews: