Page - 6
Chimney Connector Instructions
Support Box
Ceiling
Slip Connector
Locking Cleat
"B" Vent
Support Box
Slip Connector
Mid Pipe
Mid Pipe
Unit Hood
1. The slip connector section has three locking cleats located at the top of the pipe. After the support
box has been installed the slip connector is inserted into the bottom of the support box. The cleat
will lock into place as the pipe is pushed up into the support box.
2. Slip one of the mid sections over the slip connector. Slide the mid section up only enough to allow
the placement of the next section of pipe between the unit and the bottom of the mid pipe that
was placed onto the slip connector.
3. Place the remaining mid section into the collar on top of the unit.
4. Pull the mid section that is on the slip connector down into the mid section that is installed into the
unit.
Connector pipe must
be a minimum of 48"