Page 39
3.10.3. Continuation of Installation - Trim Switch Control
1. Unpack the battery pack and connect to
the battery connection on the cable.
2. Fit the connectors on the cable to the
drive motor ensuring correct polarity.
The cable connectors must be matched
to the appropriately sized spade
connector.
3. Test the operation of the drive motor
using the trim switches (
2.1.4 - Lighting
Procedure (Optimum Control and
Trim Switch Control)
on page
9
).
4. Replace the battery case under the heat
shield
5. Proceed to
Section 3.10.4
to
commission the appliance.
4xAA
BATTERIES
Figure 63
3.10.4. Continuation of Installation – Total Control
1. Unpack the box containing the receiver
and hand set.
2. Pull out the four cables through the heat
shield and connect them as shown in
Figure 64
.
3. Insert the four AA batteries in the
receiver ensuring correct polarity.
4. Replace the receiver within the heat
shield ensuring that the cables are not
touching the underside of the tray.
5. Insert the PP3 (9V) battery in the hand
set.
6. Proceed to
Section
3.10.5
to
commissioning the installation.
HT
Lead
SW
)
(yellow
TW
( )
red
Valve
Cable