Madas EVP/NC Manual Download Page 7

•  They must be installed with the arrow (on 

the  body  of  the  device)  facing  towards 

the  user  appliance.  Except  DN  200  they 

will function equally effectively if installed 

vertical. They must not be installed upside 

down (with the coil underneath).

•  During  installation  take  care  not  to  allow 

debris  or  scraps  of  metal  to  enter  the 

device.

•  If  the  device  is  threaded  check  that  the 

pipeline thread is not too long; overlong 

threads  may  damage  the  body  of  the 

device when screwed into place. Do not 

use  the  coil  for  leverage  when  screwing 

into position; use the appropriate tool.

•  If the device is fl anged check that the inlet 

and  outlet  counterfl anges  are  perfectly 

parallel to avoid unnecessary mechanical 

stresses on the body of the device.  Also 

calculate the space needed to fi t the seal. 

If  the  gap  left  after  the  seal  is  fi tted  is 

too wide, do not try to close it by over-

tightening the device’s bolts.

•  Always  check  that  the  system  is  gas-tight 

after installation.

•  Except  DN  200  in  the  version  with  fl ow 

regulator (EVPF... - EVPCF...) unscrew the 

nut (12) and set the wanted value of the 

gas fl ow by the regulation screw (13). Then 

rescrew the nut (12) in the original position.

CALIBRATIONS (DN 15 ÷ DN 150)

•  To  regulate  the  opening  speed  of  the 

obturator  operate  on  the  screw  (16). 

This  screw  has  not  limit,  the  opening 

speed  increases  gradually  screwing 

clockwise the screw (16).  

 

•  To regulate the rapide stroke operate on the 

screw  (15).  Screwing  counterclockwise 

till the limit, the opening of the valve will 

be slow at fi rst, screwing it clockwise you 

get a fi rst phase of speed opening and a 

second slow one. 

 

 

•  To  regulate  the  fl ow  operate  on  the  screw 

(14).  Screwing  it  clockwise  in  order  to 

decrease  the  fl ow,  counterclockwise  in 

order to increase it.

ELECTRICAL CONNECTIONS

•  Before making electrical connections, check 

that  the  mains  voltage  is  the  same  as 

the  power  supply  voltage  stated  on  the 

product label.

•  Disconnect the power supply before wiring. 

 

 

 

•  Wire the connector with cable type: 

   EVP...   DN 15 ÷ DN 25

   EVPC...   DN 25 ÷ DN 50

   EVP...   DN 200 

H05RN-F 3X0,75mm², Ø outside from 6,2 to 8,1 mm

   EVP...   DN 32 ÷ DN 150 

H05RN-F 3X1 mm², Ø outside from 8,3 to 9,5 mm

taking care to ensure that the device has IP65 

protection. 

 

•  Connect the power supply to terminals 1 and 

2 and the ground wire to terminal   

  .   

IMPORTANT:  with tension 12 Vdc and 

24 Vdc with energy saving connector CN-

21... observe the polarity. 

The coil is also suitable for permanent power 

supply.  In  case  of  continuous  duty,  it  is 

absolutely normal for the coil to heat up. The 

coil  should  not  be  touched  with  bare  hands 

after  it  has  been  continuously  powered  for 

more  than  20  minutes.  Before  maintenance 

work, wait for the coil to cool or use suitable 

protective equipment.

Summary of Contents for EVP/NC

Page 1: ...ch thermostat etc They can be equipped with a flow regulator and adjustable slow opening kit EC certified according to EN 161 In conformity with the 2009 142 EC Directive Gas Directive In conformity w...

Page 2: ...Environment temperature 15 60 C Max superficial temperature 85 C Protection degree IP65 Class DN 15 DN 150 A DN 200 B Group 2 Closing time 1 s Opening time 1 s Coils poliammidic resin encapsulated wi...

Page 3: ...32 003 110 V 50 Hz EVP05 002 EVP32 002 230 V 50 60 Hz EVP05 008 EVP32 008 EVP NC DN 40 12 Vdc EVP06 001 EVP40 001 24 Vdc EVP06 005 EVP40 005 24 V 50 Hz EVP06 003 EVP40 003 110 V 50 Hz EVP06 002 EVP40...

Page 4: ...spring 4 Body valve 5 Obturator 6 Seal washer 7 G 1 4 cap 8 Filter 9 Fixing screws 10 Cover or bottom 11 Electrical coil 12 Coil fixing nut or screw 13 Flow calibration screw EVPF version 14 Bottom o...

Page 5: ...Capacity diagram EVP NC P max 360 mbar 1 metano 2 aria 3 gas di citt 4 gpl 1 methane 2 air 3 town gas 4 lpg e e ne o...

Page 6: ...cause an explosive atmosphere WARNING all installation wiring maintenance work must be carried out by skilled staff The gas supply must be shut off before installation Check that the line pressure DO...

Page 7: ...on the screw 16 This screw has not limit the opening speed increases gradually screwing clockwise the screw 16 To regulate the rapide stroke operate on the screw 15 Screwing counterclockwise till the...

Page 8: ...ntrol rete pipe r seau red utenza user utilisateur punto de consumo rete pipe r seau red EXAMPLE OF INSTALLATION 2 1 Gas filter type FM 2 Over pressure slam shut off valve type MVB1 MAX 3 Gas pressure...

Page 9: ...seefig 3 4 5 6 unscrew the nut 12 or the slow opening kit 17 and remove the coil 11 Unscrew the fixing screws 9 and with care take the cover 10 off the body 4 of the valve then control the obturator...

Page 10: ...12V RAC ES CN 2110 RADDRIZZATORE Energy Saving RECTIFIER Energy Saving 24 Vdc BO 0417 BO 0417 24V RAC ES CN 2100 NORMALE Energy Saving NORMAL Energy Saving 24 V 50 Hz BO 0417 BO 0417 24V RAC ES CN 21...

Page 11: ...rgy Saving DN 65 DN 80 P max 360 mbar 24 Vdc BO 1110 24 Vdc DN 65 80 CN 2000 NORMALE NORMAL 24 V 50 Hz BO 1115 24 Vac DN 65 80 CN 2010 RADDRIZZATORE Energy Saving RECTIFIER Energy Saving 110 V 50 60 H...

Reviews: