3
2.5
Install the outlet tray, length stop device
and mobile coolant trays.
Install the outlet tray and stop bar on to the
machine after setting up the machine already as
below steps:
1. Assemble the new outlet tray on to the
machine by screw in the four screws on the
both side as picture. Tighten the four screws
after make sure the top of outlet surface same
as table.
2. Install stop device on to the outlet tray at the
right side by tighten four screws.
3. If miter cutting on the front way or move the
vise to this side for another way miter cutting,
the movable cover on the left side can be
removed by pull handle up and out as arrow
direction to remove it from being cut.
Remove mobile cover by lift handle up and pull it
out from the base as showing direction.
There are four slots on the cover base after
removing the mobile cover for this way miter
cutting.
Install the mobile cover to the four slots and push
it to the right side to secure it.
4. They are two mobile coolant trays can be
moved and used in miter cutting on front and
rear side to prevent coolant spray on to the
floor.
2.6
Securing to foundation
Position the machine on a flat and level
foundation of reinforced concrete. Level machine
and anchor it to the foundation with anchor bolts.
Maintain a minimum distance of 800mm from the
rear of the machine to the wall. Position the
anchors using screws and expansion plugs or tie
rods sunk in cement.
2.7
Leveling the machine
The operating accuracy of all precision machinery
depends on the accuracy of the installation of the
machine. Manufacturing tolerance of the machine
can only be guaranteed if the machine is firmly
and properly installed. Once the machine is
lowered on the prepared foundation, machinist
levels should be used alternately on the vice slide
plates and work feed table, adjust the left to right
and front to back level of the machine with
leveling bolts.
- When leveling left to right level, adjust left side to
be approximately 3mm higher than the level of the
right side. This will provide proper return of the
cutting fluid. After proper leveling of the machine,
use anchor bolts to secure to the foundation.
Caution: All leveling bolts should support the
weight the machine evenly
Outlet tray
Mobile cover
Mobile coolant tray
Page 6
Instruction Manual for BS-461AS (B035A)
03/12/2014
Summary of Contents for BS-461AS
Page 2: ...Page 2 Instruction Manual for BS 461AS B035A 03 12 2014...
Page 17: ...Page 17 Instruction Manual for BS 461AS B035A 03 12 2014...
Page 18: ...15 SECTION A PARTS LIST Page 18 Instruction Manual for BS 461AS B035A 03 12 2014...
Page 19: ...16 SECTION A PARTS LIST Page 19 Instruction Manual for BS 461AS B035A 03 12 2014...
Page 20: ...17 Page 20 Instruction Manual for BS 461AS B035A 03 12 2014...
Page 21: ...18 SECTION B PARTS LIST Page 21 Instruction Manual for BS 461AS B035A 03 12 2014...
Page 22: ...19 SECTION B PARTS LIST Page 22 Instruction Manual for BS 461AS B035A 03 12 2014...
Page 23: ...20 Page 23 Instruction Manual for BS 461AS B035A 03 12 2014...
Page 24: ...21 SECTION C PARTS LIST Page 24 Instruction Manual for BS 461AS B035A 03 12 2014...
Page 25: ...22 SECTION C PARTS LIST Page 25 Instruction Manual for BS 461AS B035A 03 12 2014...
Page 26: ...23 Page 26 Instruction Manual for BS 461AS B035A 03 12 2014...
Page 27: ...24 SECTION D PARTS LIST Page 27 Instruction Manual for BS 461AS B035A 03 12 2014...
Page 28: ...25 Page 28 Instruction Manual for BS 461AS B035A 03 12 2014...
Page 29: ...26 SECTION E PARTS LIST Page 29 Instruction Manual for BS 461AS B035A 03 12 2014...
Page 30: ...27 Page 30 Instruction Manual for BS 461AS B035A 03 12 2014...
Page 31: ...28 SECTION F PARTS LIST Page 31 Instruction Manual for BS 461AS B035A 03 12 2014...
Page 32: ...29 Page 32 Instruction Manual for BS 461AS B035A 03 12 2014...