7.  BOOM ASSEMBLY  
 

Wipe off any dirt or grit from the coupling rings on the end of the long 3” section. Also clean the 
inside of the 4”  x 20 foot section. Lubricate the inside of the 4” tube and the coupling rings lightly 
with oil or zinc paste  Gently insert  the 3” section into the 4” boom section. Align the holes, install 
the 13/8-16 x 4-1/2” bolts and locknuts and tighten. Clean the boom tip section and slip it into the 
main section. Install the 1/4-20 x 3-1/2” bolts and locknuts. 

 
 

Install the 3/8 EYEBOLTS to the outer ends of the boom, securing with  

 

3/8-16 nuts and lock washers. Align the eyes parallel with the boom and tighten. 

 
8.   Orient the boom with the eyebolts "up”. Using a tape measure and a marking pen or masking tape, 

place a mark 1/2” in from the 

rear

 of the boom.  This will be where you position the back edge of 

the clamp plate for element #1.  Now measure forward 98” from that mark and make another mark 
for element #2. Continue marking the locations of all the elements using the element spacing 
figures given on the Dimension Sheet. 

 
9.  Attach Element #1, the linear loaded element, to the boom. For ease of element installation, 

support the boom about 3’ above ground, eyebolts "up." Slip Element #1 over the rear of the boom, 
placing the back edge of the rear plate on your first mark. ALIGN  the elements horizontal 
perpendicular to the eyebolts and tighten bolts EVENLY and firmly. Use element #1 as the element 
alignment reference. 

 
10. Mount element #2 and align and tighten as before.  Note it is usually easier to begin installing the 

phasing lines at this time between each new element mounted. Mount the next to the longest pair 
as shown on the dimension sheet. Hold the spacer in place loosely around the boom with a large 
nylon tie but don't tighten it yet.  Adjust phasing lines so that their bends are even and the lines run 
parallel to the boom.   

 

 

ALSO ATTACH THE 13 TURN COIL ACROSS ELEMENT #1  Tighten only the clamps on Element #1 

at this time. After installing element number #3, then install the longest set of phasing lines 
between #2 and #3 and tighten the clamps at Element #2, and so on. Continue until you get to 
element #8 where the 4:1 BALUN is attached.  Add the two 3 turn COILS  to the balun and attach 
the other end of the coil leads to the bolts that tighten the rod clamps. 

 
11. Now mount the DIRECTOR as shown on the DIMENSION SHEET. Align the completed elements 
 

as required with the element #1 at the other end of the boom. 


 

Attach the BOOM TO MAST PLATE using 4 more 4” machined saddles. Mount the plate at the end 
of the 4” boom section.  This should be close to the physical balance point as well. Reshape the 
phasing lines as needed to clear the plate by at least 1/2”. 

8-30LP9 ASSEMBLY MANUAL 

Summary of Contents for 8-30LP9

Page 1: ... log periodic is a rugged versatile performer designed for years of trouble free service Ma chined aluminum element to boom clamps and solid fiberglass rod center insulators are just a few of the unique structural features in this remarkable antenna The 8 30LP9 is a single antenna system that matches up with today s modern solid state equipment Maritime Government Commercial MARS and Scientific us...

Page 2: ...addles hold the 1 1 4 diameter fiberglass rod center insulators and the plates mount on the boom with 4 saddles Element 1 and 2 have 3 4 vertical support risers Element 3 does not The center insulator is 1 1 4 diameter Push on two 1 1 4 poly rings and center them at just over 6 apart Set this assembly on the 1 1 4 aluminum saddles and add the top saddles Hardware for this whole assembly is shown o...

Page 3: ...s grounded to the boom A 7 8 x 30 sleeve couples the two 3 4 element halves together with the same bolts that hold the bottom saddles Assemble loosely at this time LOG PERIODIC ELEMENT ASSEMBLY 1 REFER TO ELEMENT ASSEMBLY SHEET 2 Start with the smallest elements Elements 8 7 6 and 5 are similar There are two halves to each element Do the following for both halves Locate and install a 1 hole ELEMEN...

Page 4: ...clamp block with a 1 1 4 hole at 1 4 from the butt of the element Align with element hole as before and secure using an 8 32 x 1 3 4 screw and locknut Add the small clamp block and 1 4 20 x 1 flat head bolt and locknut loosely If it is not already there insert a 1 1 8 x 20 sleeve in the butt of the element and hold in place temporarily with a 1 4 20 x 1 3 4 bolt and locknut but don t tighten yet C...

Page 5: ...8 30LP9 DIMENSION SHEET ...

Page 6: ...8 30LP9 ELEMENT ASSEMBLY ...

Page 7: ...f Open the 5 16 turnbuckles till just one thread shows inside the body of the turnbuckle Add a thimble to each turnbuckle eye and secure the cable at each turnbuckle with two clips 6 Element 1 is last and requires the most attention SEE LINEAR LOADED ELEMENT ASSEMBLY drawing This element is almost the same as 2 except for the linear loading Prepare the element as shown except for the linear loadin...

Page 8: ...LINEAR LOADED ELEMENT ASSEMBLY ...

Page 9: ... the rear plate on your first mark ALIGN the elements horizontal perpendicular to the eyebolts and tighten bolts EVENLY and firmly Use element 1 as the element alignment reference 10 Mount element 2 and align and tighten as before Note it is usually easier to begin installing the phasing lines at this time between each new element mounted Mount the next to the longest pair as shown on the dimensio...

Page 10: ...buckles now or at the time of installation on the tower 13 Check ALL hardware for tightness Check ALL element sections especially tip sections for correct placement Make any final adjustments to linear loading tension 14 Attach feedline section to balun Route from element 8 back to boom to mast plate Secure at regular intervals with tape or nylon ties 15 When mounting this log periodic on a tower ...

Page 11: ...ent section 3 4 x 049 x 48 SOE 2 Element tip section 3 4 x 049 x 52 50 2 Element tip section 3 4 x 049 x 33 00 2 Element section 1 2 x 049 x 62 0 2 Element tip section 1 2 x 049 x 60 0 2 Element tip section 1 2 x 049 x 58 50 2 Element tip section 1 2 x 049 x 53 625 2 Element tip section 1 2 x 049 x 45 0 2 Element tip section 1 2 x 049 x 34 0 2 Element tip section 1 2 x 049 x 32 0 2 Rod phasing 3 1...

Page 12: ... 3 4 x 3 0 Delrin black 7 Linear loading arm 375 x 1 5 x 4 0 1 hole 4 LL Shorting bar halves 1 4 x 3 4 x 6 4 Insulator stabilizer bar 1 4 x 1 x 6 black ABS bar 2 Support arm for stabilizer bar 375 x 1 50 x 2 875 alum 1 1 4 hole 2 Turnbuckle plate 2 x 5 x 3 16 1 Balun mounting L bracket 2 x 4 5 x 1 8 1 Eyebolt 3 8 x 6 forged 2 Eyebolt 1 4 20 x 2 1 2 zinc 2 Turnbuckles 3 8 eye and jaw forged 2 Turnb...

Page 13: ...20 x 1 1 2 stainless 8 Bolt 1 4 20 x 1 1 4 stainless 4 Bolt 1 4 20 x 1 stainless 4 Screw 1 4 20 x 1 countersunk flathead stainless 16 Nut 1 4 20 locking stainless 68 Screw 8 32 x 2 panhead stainless 6 Screw 8 32 x 1 3 4 panhead stainless 18 Screw 8 32 x 1 1 2 panhead stainless 26 Screw 8 32 x 1 1 4 panhead stainless 40 Screw 8 32 x 1 0 panhead stainless 42 Nut 8 32 locking stainless 132 Set screw ...

Reviews: