Continue assembling the walls log by log following the diagrams. When you have fitted four logs on each
wall, install the doors with their frames. The door has a frame with the shape of the letter U, which is fitted
straight into its place from above (the hinges outside). The door frame has an adequate tolerance so that the log
will fit in. If the door does not fit in easily, check if the logs and the battens of the frame are straight. Do not use
too much strength in order not to break the frame.
Continue assembling the log framework and finish the 7th log frame. Notice that the 8th logs are already
shorter because of the window frames. Follow the precise wall diagram, walls A, B, C, D, E, F.
Continue assembling the log framework until you reach the 10th or 11th log and fit the windows to their places
the same way as the door making sure that they do not fall down.
Please make sure to install the
windows right side up. If installed upside down, the window will fall when opened.
Continue assembling the walls according to the wall diagrams. Please note that the last logs
at the front
and rear walls are longer.
Note!
A8/C3
When you have completed the walls, assemble the
to their places. It is advisable to have 1 or 2
persons helping you and to make sure that the wind cannot fall down the gable triangles before
have been installed. Note, that the small window upstairs is installed before
mounting the triangle F6.
The purlins have been slotted. They will fit into the slots of the gable triangle so that the purlin is on the
same level as the edge of the gable triangle
when installed. Fasten the purlins with
nails according to the
.
gable triangles
the purlins /
other supporting elements
picture 5
Screw the wall timbers A8 and C3 to the
gable triangles using 2 screws/corner
(predrill!).
.
Picture 12
7
Lillevilla 100 C-3 English 220109
12.
5.
gable
triangle
A8/C3