The Battery Management System will generate a Major
Battery Alarm (MJB) if the Major Temperature Alarm
(MJT) is active. The MNB and MJB alarms will be
connected to the RMN and RMJ alarm inputs,
respectively, on CP1.
2. Connect the opposite end of the black wire (MNB) to
RMN (TB101-5) and the white wire (MJB) to RMJ
(TB101-4) on CP1 (See ECS-6 Controller Product Manual,
167-790-031, Section 3.3.1 for proper connection
technique).
Installing CP3
Cable Set
1. If CP3 is present, do not install the CP1 cable set.
2. Place CP3 cable set near P400 on CP5, but do not connect
to CP5 at this time. Route as shown in Figure 3-10.
3. Connect the opposite end to unused analog channels on
CP3. See Section 3 of ECS Controller Options Product
Manual (167-790-109) for proper connection technique.
Signals on each pin of P400 are shown in Table 3-A. See
Section 5.2.1 through 5.2.4 of this manual for proper
datalogger channel configuration.
.