Functional test with LPKF BoardMaster
ProtoMat C30/C30-S
21
7.0 Functional test with LPKF
BoardMaster
Danger! Make sure that no other persons are working on the
machine when the first functional test is taking place.
First check that the parameters for the serial port:
• 9600 baud
• 8 data bits
• 1 stop bit
• no parity bit
• hardware handshake
• FIFO off.
Also check that the correct interface has been selected in
BoardMaster
under
CONFIGURATION, INTERFACE...
. Consult the
BoardMaster
Manual if you require assistance. The remainder of the procedure is
carried out using
BoardMaster
:
fig. 6:
1.
Move the head manually using the cursor keys on the
BoardMaster
toolbar (
3
).
2.
Switch on the motor. (
1
)
(The motor runs at low speed during the warm-up phase)
3.
Wait for the warm-up phase to complete.
4.
Lower/raise the head (
2
).
5.
Switch off the motor (
1
).
6.
Check the interface configuration, the connecting cable and the PC
interface if the equipment does not move.
Note: The motor cannot be switched off when the machine is in the
tool change position.
Summary of Contents for ProtoMat C 30-S
Page 72: ...Index 72 ProtoMat C30 C30 S...