background image

SMARTNEO-2G: CASCADING MANUAL // PAGE 21

9  ADDITIONAL INFORMATION

9.1  CHANGING A CASCADING SYSTEM

Before any changes to a Cascading System are made, ensure both Control Boxes have been disconnected 
from the Power Source. 

After changing a Cascading System, you may need to perform a Factory Reset. Go to Chapter 7.2 for further 
instructions. 

9.1.1  REPLACING A CONTROL BOX

To exchange Control Boxes in an existing Cascading System, proceed as follows:

1.  Reset both Control Boxes to factory settings, see chapter 7.2. (Optional: Can also be performed 

after reconnection).

2.  Disconnect the Control Boxes from the power source
3.  Use the instructions in Chapter 6 to connect the components to the new Control Box

9.1.2  REPLACING AN ACTUATOR

To replace Actuators in an existing Cascading System, proceed as follows:

1.  Disconnect the unwanted Actuator from the Control Box
2.  Connect the new Actuator to the Control Box
3.  Perform a Reference Drive, see chapter 7.1

9.1.3  UNGROUPING A CASCADING SYSTEM

1.  Reset the Control Boxes to factory settings, see chapter 7.2. (Optional: Can also be performed 

after reconnection).

2.  Disconnect the Control Boxes from the power supply
3.  Disconnect the cables

9.2  MAINTENANCE

All components in the Cascading System are maintenance-free for their entire service lifetimes. If cleaning 

of any product required, wipe its housing with a soft, dry cloth. 

9.2.1  DISPOSAL

The SMARTneo-2G is an electrical and electronic device that must be disposed of separately 
from household trash in accordance with the WEEE directive 2012/19/EU. Products of this 
type are labelled with the symbol shown on the left.

Before disposing of materials and components, check their recyclability. Recycle all parts if 
possible. Dispose of all materials and parts according local guidelines and regulations. Ensure 
that the disposal is lastingly compatible for humans and nature.

Summary of Contents for SMARTneo-2G

Page 1: ...MANUAL Document Version 1 0 July 2019 SMARTneo 2G Cascading...

Page 2: ...rman language version is the original LOGICDATA Electronic Software Entwicklungs GmbH Wirtschaftspark 18 8530 Deutschlandsberg Austria Phone 43 0 3462 51 98 0 Fax 43 0 3462 51 98 1030 Internet http ww...

Page 3: ...t documentation before connecting the components to form a Cascading System and putting it into operation Required components For detailed instructions see the Required Components subchapter for your...

Page 4: ...g System with 2 Actuators For detailed instructions see chapter 6 3 5 on page 15 1 2 SA VE 3 4 1 2 SA VE 3 4 Cascading System with 3 Actuators For detailed instructions see chapter 6 6 on page 16 1 2...

Page 5: ...nstructions see chapter 6 7 on page 17 1 2 SA VE 3 4 1 2 S A V E 3 4 Performing the Reference Drive For detailed instructions see chapter 7 1 on page 18 O73 Factory Reset For detailed instructions see...

Page 6: ...5 Explanation of symbols and signal words 10 3 6 Liability 10 3 7 Residual risks 11 3 8 Skilled Persons 12 3 9 Notes for Resellers 12 4 Scope of delivery 12 5 Product 13 5 1 About Cascading 13 5 2 Ab...

Page 7: ...the Components 17 7 Operation 18 7 1 Reference Drive 18 7 2 Factory Reset 18 7 2 1 With a Basic Hand Control 18 7 2 2 With a Comfort Hand Control 19 8 Troubleshooting 20 8 1 Lexicon 20 8 2 Possible P...

Page 8: ...After purchase and full payment of the product all text and images in Chapter 3 Safety may be used free of charge by the customer for 10 years after delivery They should be used to prepare end user d...

Page 9: ...is a Control Box for electrically Height Adjustable Tables It is intended for indoor use only The system may only be installed in compatible Height Adjustable Tables and with LOGICDATA approved acces...

Page 10: ...r sources INFO Indicates important tips for handling the product 3 6 LIABILITY LOGICDATA products comply with all currently applicable health and safety regulations However risk can result from incorr...

Page 11: ...ks While cleaning or using the system liquid intrusion may lead to serious injury through electric shocks Do not allow any components to become wet during cleaning Ensure components are placed away fr...

Page 12: ...l in their native EU official language INFO The Charter of the French Language La charte de la langue fran aise or Bill 101 Loi 101 guarantees the right of the population of Quebec to conduct business...

Page 13: ...also dependent on parameterization NOTICE This Cascading Manual is only valid for the SMARTneo 2G 2nd generation Consult your product s Datasheet and Type Plate to ensure this is the correct Manual f...

Page 14: ...risk of death or serious injury through electric shocks Using damaged products may lead to death or serious injury through electric shocks Do not operate the Cascading System if you see housings or c...

Page 15: ...n each system 1 LOG CBL SMARTneo SYNC 1000 Sync Cable 2 Power Cables 6 5 2 CONNECTING THE COMPONENTS 1 Connect the first Actuator to a Control Box M1 2 Connect the second Actuator to the second Contro...

Page 16: ...h system 1 LOG CBL SMARTneo SYNC 1000 Sync Cable 2 Power Cables 6 6 2 CONNECTING THE COMPONENTS 1 Connect the first two Actuators to a Control Box M1 and M2 2 Connect the third Actuator to the second...

Page 17: ...LOG CBL SMARTneo SYNC 1000 Sync Cable 2 Power Cables 6 7 2 CONNECTING THE COMPONENTS 1 Connect the first two Actuators to a Control Box M1 and M2 2 Connect the third and fourth Actuators to the secon...

Page 18: ...erence Drive must be performed after the Cascading System has been connected for the first time Ensure that all components are connected correctly Press and hold the DOWN Key The Actuators start up at...

Page 19: ...settings It is now in the same state as it was during the first start up INFO Resetting the Master Control Box in the system to factory settings will automatically reset the Slave Control Box INFO If...

Page 20: ...r 8 2 POSSIBLE PROBLEMS AND THEIR SOLUTIONS Error code malfunction Possible cause Solution E7O Actuator configuration has been changed Disconnect the Control Boxes from the power supply for approx 30...

Page 21: ...tor from the Control Box 2 Connect the new Actuator to the Control Box 3 Perform a Reference Drive see chapter 7 1 9 1 3 UNGROUPING A CASCADING SYSTEM 1 Reset the Control Boxes to factory settings see...

Page 22: ...rk 18 8530 Deutschlandsberg Austria Phone 43 0 3462 5198 0 Fax 43 0 3462 5198 1030 Email office at logicdata net Internet http www logicdata net LOGICDATA North America Inc 1525 Gezon Parkway SW Suite...

Reviews: