background image

10

3N1

PREPARATION OF CABLING

SCU Side

Power supply 24 V
Ground
4K
LAN to Q-Board

The power supply must be installed by an electrician

Cabling SCU Front

1.  Drill 4 holes Ø 5mm and deburr.
2.  Install the power supply as shown. Mounting parts and 

cable ties are provided

3.  Fix the power input and power output cables with the ca-

ble ties to the power supply, as shown.

4.  Make sure that the cables are tied at the cable mantle and 

not at the wires.

Power Supply connections

Power Supply mounting

4x spring washer M4 DIN6798
4x screw M4x10 DIN7985

Preparation of Major Cabling 

Summary of Contents for A905262

Page 1: ...YARNMASTER 3N1 46261003en Fitting Instruction Schlafhorst ACO240...

Page 2: ......

Page 3: ...further company and product names are trading names or registered trademarks of the relative companies The content of this Operating Instruction is protected by cop yright All rights reserved No part...

Page 4: ...4 3N1 INHALTSVERZEICHNIS...

Page 5: ...N1 9 Preparation of Major Cabling 10 SCU Side 10 Power Supply Connection 11 LAN to Q Board 12 Connection 4K to SCU 13 Fitting of Sensors 14 Cabling of the Section Electronic SE 16 Connections to SAG 1...

Page 6: ...3N1...

Page 7: ...tes warnings which if not properly observed could harm your health impair the functioning of the equipment or the security of your data Note The screen representations in this manual serve as illus tr...

Page 8: ...tic charges Be ware of touching the soldered connectors pin contacts be fore they have been discharged statically Hold the units at the periphery only Upgrade works must be carried out with switched o...

Page 9: ...Time instructions based on 240 Rotors Time for Approx man hours Deinstallation of old system 14 Installation of 3N1 full and basic 36 Time for Hours Start up 5 Time for only one time Hours Teaching 8...

Page 10: ...ll the power supply as shown Mounting parts and cable ties are provided 3 Fix the power input and power output cables with the ca ble ties to the power supply as shown 4 Make sure that the cables are...

Page 11: ...ne or external White Power supply for SCU 24V 30W only use one of the outputs Power To be connected with an external power supply or have it connected to the machine electronics by an electri cian Pow...

Page 12: ...else with an as sured ground White power cable for power supply front side as installed Black power supply from machine or external Remove the cover Use the cable track to fit the cable before you fe...

Page 13: ...13 3N1 PREPARATION OF CABLING Connection 4K to SCU Red 4K 4K cable to 4K card inside of the Informator The card is written down...

Page 14: ...ece to the sensor Screw the sensing head into the existing hole of the bar Pic ture 1 and position it in the middle of the hole of the mount ing piece Picture 2 It is necessary to do it in this way to...

Page 15: ...should be in the range of the press roller Picture If this is not so the metal bar with with screwed on sensor should be slided This should be done by the mill mechanics To do this the adjusting parts...

Page 16: ...pply unit Black 1 2 Power supply 24V for SE Yellow LAN to SE boards splitter on each section Red Start Stop cable IF to connect the SAG For exact cabling see the following description Before starting...

Page 17: ...ns to SAG Red Q Stop cable each for one side 12 rotors The SAG board requires an Interface print It can be simply plugged on Position 1 to connector lower connector on the SE Board Position 2 to conne...

Page 18: ...nductor can be pow ered by Schlafhorst or externally A first cable is laid from this power supply up to the first empty shaft door There it is con nected to the serial line which must be laid into the...

Page 19: ......

Page 20: ...RONIC SE Q Board Connections Red Stop cable Lower for SAG Board IF connector number 1 Superior for SAG Board IF connector number 2 White Power supply 24 V from SAG Yellow LAN to SCU is splitted by eac...

Page 21: ...AN for Q Board Earthing of SE Board The screw must be screwed onto the Q Board at the upper left side as illustrated The earthing is assured by the cable channel Above the opening at the end of the se...

Page 22: ...r As soon as the Q Boards are placed the attached stickers must be fixed This marking serves for a correct cabling and helps in case of exchange Blue SE Board number Yellow first and last rotor number...

Page 23: ...to Q Board 6 cables length 2m shorter way to Q Board Cable from the sensor to the inside of the machine Use the support different types available Inside view of the backside of the rotor Labling of s...

Page 24: ...tor position 3 6 9 11 starts from the section beginning Option 2 Cable Channels For both sensor cable layings an orderly laying is necessary to avoid unnecessary loops Option 1 Tie Wraps Fit the cable...

Page 25: ...pin10 J44 and pin10 J45 Output voltage 12V 5 Maximum output current 100mA connector High side outputs J48 J49 Type of output open collector number of outputs 2 x 12 outputs Max output current output...

Page 26: ...Loepfe Brothers Ltd 8623 Wetzikon Switzerland Phone 41 43 488 11 11 Fax 41 43 488 11 00 info loepfe com www loepfe com Subject to technical modifications...

Reviews: