background image

6  

Maintenance

Hot Water Generator Installation and Operation Manual

Storage tank maintenance

A new tank installation should have a regular inspection
program set up. The first inspection should be within the first
three months of operation. Once the tendency to accumulate
sediment has been established, the inspection program can be
modified to suit the water conditions. Typical inspection
programs flush the tank at six-month intervals and clean the
tank in yearly intervals.

Deliming solvents or acid type flush agents are not
recommended for use in lined storage tanks. These chemical
cleaners are usually designed for use in non-potable systems
such as heating boilers. These chemicals may be aggressive
and cause damage to the tank lining and deteriorate the
magnesium anodes supplied in glass-lined storage tanks.

WARNING

Hot water will be released under pressure.
Avoid contact with the hot discharge water
to prevent the risk of severe scald injury.

Flushing the storage tank

Since the mineral accumulation is occurring in an un-fired
tank it will be in a soft sediment form. This soft sediment can
be removed by a regular flushing of the lower portion of the
tank.

To flush the tank, follow these steps:

1.

Turn off electrical power to the circulating pump and any 
other tank accessories.

2.

Close the valve on the hot water outlet on the top of the 
storage tank.

3.

Ensure that the drain located on the bottom of the tank 
is routed to a floor drain with adequate capacity to allow 
the tank to be flushed.

4.

Open the drain valve and allow the incoming cold water 
to flush the soft sediment out the bottom of the storage 
tank. Use extreme caution, as the water exiting the tank 
drain may be very hot. Avoid contact with the hot 
discharge water to prevent the risk of severe scald injury.

5.

Observe the color of the water initially discharged from 
the tank drain. This water will generally be milky or 
slightly discolored by the sediment discharge. Allow the 
drain to run until the water runs clear.

6.

Close the drain valve on the tank.

7.

Open the hot water outlet valve on the top of the tank.

8.

Open an adjacent hot water tap to purge any air that may 
have entered the storage tank during the draining 
process. Close the hot water tap if no air discharge is 
observed.

9.

Turn on electric power to the circulating pump and other 
electrical components if necessary.

10. Observe tank and piping to ensure all components are 

functioning properly.

Cleaning the storage tank

The mineral accumulation in an un-fired tank will be in a soft
sediment form that can be removed by a regular cleaning of
the lower portion of the tank. Many tanks will have a hand
hole or a larger manway to allow access to the interior of the
tank for complete removal of accumulated sediment. An
access opening to remove the manway or hand hole is
provided in the exterior jacket.

The sheetmetal jacket

components are removed with hand tools. The opening will
be in the bottom portion of a vertical tank and on the end of
a horizontal tank (see FIG’s 1 and 2 on page 4 of this manual).

To clean the tank, follow these steps 

(reference FIG.’s 7 and 8)

:

1.

Close valves from boiler water or steam supply and 
return or condensate pipes.

2.

Turn off electrical power to the circulating pump and 
other electrical components if necessary.

3.

Close the valve on the hot water outlet on the top of the 
storage tank and the cold water supply to the system.

4.

Ensure that the drain located on the bottom of the tank 
is routed to a floor drain with adequate capacity to allow 
the tank to be drained.

5.

Open the drain valve and open a vent to allow the air to 
enter the tank (manually opening the relief valve will 
usually accomplish this). Use extreme caution, as the 
water exiting the tank drain may be very hot. Avoid 
contact with the hot discharge water to prevent the risk 
of severe scald injury.

6.

Allow the tank to drain completely.

7.

Remove the jacket cover over the manway or hand hole.
Remove the bolt(s) securing the tank access opening.
Use a flashlight to observe the sediment collected in the 
tank.

8.

Use hand tools to remove all sediment  from the interior 
of the tank. Use care not to damage the interior lining of
the storage tank.

9.

Use a water hose to flush the remaining sediment from 
the interior surfaces of the tank and ensure that all debris 
is removed.

Scale or sediment allowed to reach the 

potable system can foul valves, pumps, strainers, and 
other water fixtures. Ensure that the tank interior is clean 
before refilling the vessel.

15

Summary of Contents for Hot Water Generator

Page 1: ...ion contained in this manual is intended for use by qualified professional installers or service technicians Consult your local expert for proper installation or service procedures WARNING Save this manual for future reference Unit shown with optional control package ...

Page 2: ...mportant information concerning the life of the product DANGER WARNING CAUTION CAUTION NOTICE DANGER indicates an imminently hazardous situation which if not avoided will result in death or serious injury WARNING indicates a potentially hazardous situation which if not avoided could result in death or serious injury CAUTION indicates a potentially hazardous situation which if not avoided may resul...

Page 3: ...ey are installed Hot Water Generator Systems are available in horizontal or vertical configurations see FIG s 1 and 2 in a wide array of gallon capacities Standard packages are available in tank sizes from 200 1000 gallons with single wall copper tube bundle heating units Custom configurations smaller and larger tank and tube bundles and optional control packages are also available Consult the fac...

Page 4: ...and outlet wye strainers a float and thermostatic steam trap and all necessary piping Water to Water Control packages include isolation valves 2 way self operated temperature regulator inlet wye strainer and all necessary piping Options Manual Reset High Limit Solenoid Valve Manway see notes on manway 150 psi Tank Working Pressure Temperature Pressure Gauge Vacuum Breaker Figure 1_Vertical Tanks F...

Page 5: ...ves and pressure regulators 3 All power connections and cables Before attempting any installation operation or maintenance procedures pertaining to this unit 1 Assure that the incoming steam or boiler water has been turned off at the manual shutoff valve 2 If the unit has been in operation allow the water in the heater and all components and surfaces incoming steam line hot water outlet line etc t...

Page 6: ...ory after leak testing Reassembly will require re attaching the unions or bolting flange to the appropriate locations and insertion of the control valve bulb into the provided bulbwell and the system is ready for operation see FIG s 5 and 6 below All hardware for the reassembly is included with the system Drawings of the specific controls package are included with each product illustrating the fin...

Page 7: ...drawings that indicate the location and specifications for each connection that must be made In addition the drawing will enable the installer s to determine the flow direction of both the water and energy source Connecting the cold water source and the hot water outlet Before making any connections of water inlet or outlet to the unit assure that all piping is clean and free of foreign material o...

Page 8: ...f valve should be installed downstream in the condensate return line to allow the unit to be isolated from the system The condensate shutoff valve will prevent backflow of steam if the line is disconnected WARNING Do not attempt to lift condensate with a float and thermostatic trap Pipe the condensate outlet from the main steam trap to a gravity drain or to a condensate pump Lifting condensate wit...

Page 9: ...must be connected The circulation pump must run all the time Wire this pump to a correctly sized disconnect switch per local codes The combination of electricity and water can pose a very dangerous situation Assure that all electric power has been turned off before attempting any installation or maintenance procedures WARNING Reference the wiring CAD drawing included with the unit or the installat...

Page 10: ...ypass loop ball valve approximately half way Allow the system to push air out of the tube bundle and the piping slowly Note It should be noted that when the control valve is closed the boiler water will flow through the bypass loop When the valve is open less water will bypass Adjustment of the bypass loop ball valve will be necessary to balance your system For initial installation the bypass valv...

Page 11: ...ns R RE EC CO OM MM ME EN ND DE ED D I IN NS SP PE EC CT TI IO ON NS S To Be Inspected Time Interval Per Manufacturer Specs Weekly Monthly Quarterly Semi Quarterly Annually Circulating Pump Control Valves Temperature Pressure Gauges Pressure Temperature Lines Inlet Outlet Return Power Connections Pressure Relief Valve Shutoff Valves Manual Single Solenoid Safety System Strainers Temperatures Water...

Page 12: ...gn pressure for energy source in the tube bundle as the temperature of the water in the tank heater approaches shutoff Reconfigure the condensate water return piping and check valve to allow for proper drainage Check to assure that there is no restriction in the condensate water drain line Replace the check valve if it is leaking or has failed Also check to assure that there is no restriction in t...

Page 13: ...he tank heater approaches shutoff Reconfigure the condensate water return piping and check valve to allow for proper drainage Check to assure that there is no restriction in the condensate water drain line Replace the check valve if it is leaking or has failed Also check to assure that there is no restriction in the condensate water drain line Verify control valve bulb was installed in the bulbwel...

Page 14: ...stem has failed Check the individual components of the system and repair or replace the failed component s as necessary A loud banging in the water heater primary piping or condensate water return piping not to be confused with a normal clicking noise made during operation The condensate water return piping has not been installed properly allowing the condensate water to drain freely by gravity th...

Page 15: ... may have entered the storage tank during the draining process Close the hot water tap if no air discharge is observed 9 Turn on electric power to the circulating pump and other electrical components if necessary 10 Observe tank and piping to ensure all components are functioning properly Cleaning the storage tank The mineral accumulation in an un fired tank will be in a soft sediment form that ca...

Page 16: ...m anode rod inspection Glass lined storage tanks have a magnesium anode s to provide cathodical protection of the lining and minimize corrosion Aggressive water conditions in some areas of the country may accelerate the deterioration of the anode s The anode s should be periodically removed and inspected to determine if replacement is necessary The tank must be valved off from the system and fully...

Page 17: ...nce FIG 9 to assure proper wiring 9 Follow the startup procedures page 10 to put the unit back on line Carefully check all connections for any sign of leakage Circulating pump shutoff valves replacement If the Lochinvar Hot Water Generator is equipped with a circulating pump to assist in the even heating of the water manual shutoff valves will be located on both the inlet and outlet side piping To...

Page 18: ...y drained that the pressure has been bled from both the water and energy source systems and that the water all components and surfaces have cooled 3 Carefully break the connections between the tube bundle head and the energy source inlet and outlet lines WARNING It may be necessary to break the lines at a second location and for the lines to be rotated to allow clearance for the tube bundle to be ...

Page 19: ...e damaged section of line or valve 6 Reconnect the line or valve to the unit Follow recommendations contained in the manufacturer s documentation local codes or accepted contractor practices as to the use and or type of joint compound or sealer at the connections 7 Follow the startup procedures page 10 to put the unit back on line Carefully check all connections for any sign of leakage Single sole...

Page 20: ... it is necessary care should be taken to ensure that in line components are not damaged 7 Remove the temperature control valve from the system 8 Follow the supplied manufacturer instructions for inspecting the valve If found to be malfunctioning replace the valve 9 Carefully replace the temperature control valve into the system by reattaching it to the energy source inlet line and the tube bundle ...

Page 21: ...ning properly and must be replaced follow the procedure outlined below WARNING The combination of electricity and water can pose a very dangerous situation Turn off disconnect all electric power before attempting any maintenance procedure 1 Follow Steps 1 through 5 of the shutdown procedure page 10 to take the unit off line before attempting to replace the main or auxiliary traps 2 The exact locat...

Page 22: ...22 Hot Water Generator Installation and Operation Manual 7 Notes ...

Page 23: ...23 7 Notes Hot Water Generator Installation and Operation Manual ...

Page 24: ...HWG i o 01 CP 2M 12 05 ...

Reviews: