First Fix Kit
–
Cabling
Power Requirement (Mains)
Liquifi
requires a 1
0
amp socket outlet connected to a 240 V mains supply via a readily
accessible isolation switch. This electrical installation must include an all-pole switch with a contact
separation of at least 3 mm in each pole. Both the socket and the isolation switch must conform to
the latest safety specification and be protected via an RCCD device or similar. This socket must be
fitted in a dry area, away from any moisture (usually in the ceiling). The mains plug must be fitted
with a 5 amp fuse..
- 11 -
Please
note
–
All electrical installation should be carried out by a fully qualified
electrician and all fire & safety regulations must be obeyed.
Installation and Positioning
Further details can be found on the back of each screen.
Universal VESA Wall Mount:
The wall must be strong enough to hold at least 100kg.
VESA Mount (optional)