daTa CoMMunICaTIons

rs-232 or rs-485 Communications 

The LCR-II 840405 CPU board can communicate using RS-232 or RS-485 communication protocol. Data connections 

are protocols is made at the J2 and J3 terminal blocks. For standard RS-232 terminal, (other than the Lap Pad), the 

red  input wire should be connected to J3-47. 

A jumper (J10), located on the left side of the CPU board should stay in the B position for most applications; however, 

to use a lap pad (PN E40301 and E403011) the jumper must be moved to the A position. See the diagram and the 

table below. 

PRINTER

SERIAL 485

TERMINAL

POWER

COUNTER

MH1

CTS RXD TXD RTS

GND

GND

485+A

485-B

CTS RXD TXD RTS +VP

EARTH

AUX OUTPUTS

PULSE INPUTS

AUX I/O

GND

GND

GND

IN 1

OUT1

OUT2

OUT3

TEMPERATURE PROBE

ASSY

84040 REV.

RTD+S

RTD-D1

RTE-S

RTD+D

OUT4

OUT5

IN 2

IN 3

IN 4

+5V OUT

+VP

+VP

PGND

OUT6 +VP

SOL

+VP

PGNDOUT7

+VF

+VF

IN5

OUT8

GND

GND

+12-24V

ACC

MH4

C1

J20

J6

J3

J2

J1

J7

J12

J15

P1

TP1

J5

J14

J18

J19

J10

J17

J11

J7

C2

MH5

MH3

MH2

A

B

11

10

1213

52

53

54

55

56

A

B

A

B

J2 (RS-485)

J3 (RS-232)

A Position

B Position

24

25

juMPer PosITIon 

(j10)

CoMMunICaTIon 

ProToCol

WIre

Lap Pad

A

RS-232

J3 - 46 (red)

Flashing Software on the CPU Board 

EZCommand

B

RS-232

J3 - 47 (red)

External Computing Device

B

RS-232

J3 - 47 (red)

External Computing Device

B

RS-485

J2 - 24 (red)

J2 - 25 (violet)

Multimeter Network

B

RS-485

J2 - 24 (red)

J2 - 25 (violet)

PoWer InsTallaTIon 

Power Installation overview 

When you have made all of the data connections and finished installing all of the components, connect the power to 

the LCR-II and the Epson printer. But before making the power connections, go through the vehicle system checklist 

below, and ensure that the electrical system of the truck meets the minimum requirements for powering the LCR-II 

and the Epson printer.

vehicle system Checklist

 

□  Clean any corrosion from the battery terminals and battery cable to guarantee a solid, tight connection.

 

□  Charge the battery in accordance with the manufacturer’s specifications.

 

□  Ensure the alternator is large enough to meet the total demands of the truck, including the LCR-II. The LCR-II  

 

requires a minimum of 5 A for proper operation. Run the truck at low idle with all accessories on (including  

 

hose reel), and check the voltage with a multi-meter. The voltage should not drop below 11 V.

 

□  Inspect the electrical equipment on the vehicle, and ensure it is properly installed and operating correctly.

 

□  Determine whether the vehicle is grounded positively or negatively. Consult Liquid Controls if the vehicle 

 

 

has a positive ground.

 

□  Make sure that any radio antennas are installed in accordance with the manufacturer’s specification to    

 

prevent RF  interference.

The J2 terminal block is 

permanantly attached to the 

CPU board.

Do Not Try To Remove J2

Summary of Contents for LectroCount LCR-II E3657 Series

Page 1: ...LectroCount LCR II Installation Liquid Controls An IDEX Energy Fuels Business Operation EM150 21 E3657 E3658 Series LectroCount LCR II SELECT INCREASE Gallons S3...

Page 2: ...se 2 ou une alimentation lectrique isol e et comportant un dispositif de protection contre la surtension de 5 amp res ou moins sont requises pour l installation Peripheral equipment must be suitable f...

Page 3: ...a known good ground less than 1 Use a 12 ga or larger stranded wire Fixed Installations LectroCount housings directly mounted to the meter are attached to the earth ground through the meter via the ta...

Page 4: ...ower cable Specifications Safety Tag Markings EU Explosive Atmospheres symbol This equipment has been found to comply with the European Directive for Equipment For Potentially Explosive Atmospheres 94...

Page 5: ...8 Dimensions Side Front Top 15 9 94 5 19 LectroCount LCR II 13 7 5 8 04 10 5 70 Rear...

Page 6: ...ghts Measures custody transfer product delivery and ticket generation Metrological data collection Presetting by volume Multiple production selection Security settings Air and vapor elimination with p...

Page 7: ...y standard for many applications Multi layered tickets are available to provide a physical record for both customers and business records The Epson roll printer is ideal for recording multiple custody...

Page 8: ...xidation from the ground strap contact point Lock washers should penetrate any paint to ensure a good electrical connection Ensure a Good Ground LectroCount Ground Strap Kit 82185 Install the LectroCo...

Page 9: ...nd discharge line valve nozzle 8 Leave the discharge line valve nozzle open while working on the system 1 Close the belly valve of the supply tank 2 Close the valve on the vapor return line 3 Close th...

Page 10: ...es Data and Power Cable The LCR II shipment typically includes a gray 40 power cable and a 40 black data cable prewired to terminal blocks on the LCR II CPU board On typical truck installations the ca...

Page 11: ...Preset Valve Single Stage Electro Pnuematic Valve with V 7 Valve S1 Solenoid V 7 Valve Electro Pnuematic Actuator LectroCount LCR II Gallons A2859 11 Block Valve and 3 Way Solenoid Single Stage 3 Way...

Page 12: ...eries Electro Pnuematic Valve Electro pnuematic valves use a S1 solenoid operated valve mounted to a pneumatic actuator to open and close a V 7 valve These valves are typically used in high viscosity...

Page 13: ...llations When ordered as part of a meter system with a LCR II Liquid Control s optical air and vapor eliminators are bolted onto the strainer and wired to the LCR II at the factory Optical air and vap...

Page 14: ...d PN 81944 that mounts directly to the LCR II CPU board Typically a P transducer operates in conjuction with a shutdown device such as a valve or a dead man The shutdown control must be wired to the L...

Page 15: ...llation J1 RS 232 A Liquid Controls meter system with a LCR II typically includes an Epson slip printer or roll printer Installation is the same for both printers LCR II s are typically shipped with a...

Page 16: ...ng Device B RS 485 J2 24 red J2 25 violet Multimeter Network B RS 485 J2 24 red J2 25 violet Power Installation Power Installation Overview When you have made all of the data connections and finished...

Page 17: ...r the LCR II has been installed check to make sure that it powers up correctly The LCR II display and the printer power light should come on when the truck s ignition is turned to the ON or to the ACC...

Page 18: ...er provided and held in place with the cotter pin provided The control switch on the front of the LCR II is also sealed with an O ring and held in place by a bushing secured with three socket head cap...

Page 19: ...sher 2 81994 PULSER 100 PPR Pulser Field Install Kit 82597 08189 Flat Washer 08201 O ring 2 Optional Items not shown Description Part Number Roll Printer Extension Cable 71237 Flash Cable 81885 Lap Pa...

Page 20: ......

Page 21: ...2014 Liquid Controls Pub No 500392 7 14 105 Albrecht Drive Lake Bluff IL 60044 2242 1 800 458 5262 847 295 1050 Fax 847 295 1057 www lcmeter com...

Reviews: