35
lindab | we simplify construction
Smoke Control Damper
SDR
2
-M
Lindab reserves the right to make changes without prior notice
Last modified: 2021-10-26
Rev: 2021-03-26
Position:
1. Damper SDR2-M
2. Gypsum wall construction
3. Mortar or gypsum
4. Hinges
Cover of actuating mechanism
has to be removable after installation
4.4.2.
Installation in gypsum wall construction of fire compartment
Fig. 32
Example of installation in gypsum wall construction of fire compartment.
Fig. 33
Example of installation in gypsum wall construction of fire compartment.
Position:
1. Damper SDR2-M
2. Gypsum wall construction
3. Mineral stone wool, density 140 kg/m
3
4. Fire protection mastic, thickness 1mm
5. Cement lime plate, thickness 15mm,
density 870 kg/m
3
6. Hinges
Cover of actuating mechanism
has to be removable after installation