3. Evacuation
(All amount of refrigerant leaked)
• Procedure
(1) Connect the vacuum pump to the charge set’s
center hose
(2) Evacuation for approximately one hour.
– Confirm that the gauge needle has moved
toward -76 cmHg (vacuum of 4 mmHg or less).
(3) Close the valve (Lo side) on the charge set,
turn off the vacuum pump, and confirm that
the gauge needle does not move (approxima-
tely 5 minutes after turning off the vacuum
pump).
(4) Disconnect the charge hose from the vacuum
pump.
– Vacuum pump oil.
If the vacuum pump oil becomes dir ty or
depleted, replenish as needed.
Lo
Open
Open
Vacuum pump
2-Way
valve
Outdoor unit
Liquid side
Indoor unit
Gas side
3-Way
valve
CLOSE
OPEN
Summary of Contents for LS-J0766ML
Page 1: ......
Page 5: ......
Page 6: ......
Page 7: ......
Page 8: ......
Page 11: ......
Page 13: ......
Page 14: ......
Page 55: ... 2 MAIN P W B ASSEMBLY DC PART TOP VIEW 2 MAIN P W B ASM DC BOTTOM VIEW ...
Page 56: ... 3 DISPLAY ASSEMBLY 6871A20194 TOP VIEW 6871A30009 TOP VIEW BOTTOM VIEW BOTTOM VIEW ...
Page 57: ...Schematic Diagram TELEPHONE CONTROL MODEL ONLY 51 ...
Page 58: ......
Page 59: ......
Page 70: ...May 2002 Printed in Korea ...