Configuration steps for a Siemens Simatic S7 control
The following steps are necessary for commissioning with a Siemens S7 control:
1.
Preparation of the control system (S7 PLC)
2.
Installation of the GSD file
3.
Hardware configuration of the S7 PLC
4.
Transfer of the PROFINET configuration to the IO Controller (S7 PLC)
5.
Device naming
• Configuration of the device name
• Device naming
• Assigning the device names to the configured IO devices (see figure 9.5)
• Assignment of MAC address - IP address -individual device name ((see figure 9.12))
6.
Check device name