Commissioning and operation
Functional test
41
Lenze ¯ BA 33.0008 ¯ 5.0
Before initial commissioning, before commissioning after an extended standstill
period, or before commissioning after an overhaul of the motor, the following must be
checked:
¯
Measure the insulation resistance, in case of values
£
1 k
W
per volt of rated
voltage, dry the winding.
¯
Have all screwed connections of the mechanical and electrical parts been firmly
tightened?
¯
Is the unrestricted supply and removal of cooling air ensured?
¯
Has the PE conductor been connected correctly?
¯
Have the protective devices against overheating (temperature sensor evaluation)
been activated?
¯
Is the inverter correctly parameterised for the motor?
(
,
Inverter operating instructions)
¯
Are the electrical connections o.k.?
¯
Does the motor connection have the correct phase sequence?
¯
Are rotating parts and surfaces which can become very hot protected against
accidental contact?
¯
Is the contact of good electrical conductivity if a PE connection on the motor
housing is used?
7.3
Functional test
¯
Check all functions of the drive after commissioning:
¯
Direction of rotation of the motor
–
Direction of rotation in the disengaged state (see chapter "Electrical
connection").
¯
Torque behaviour and current consumption
¯
Function of the feedback system