Chapter 3: Installing NE2580O Hardware and Options
49
3.
Secure the air-duct mounting bracket to the rails with M6 screws. Torque the
screws to approximately 5.7 Nm ± 0.1 Nm (50 inch-pounds).
Note:
Reuse the original M6 screws used to fasten the 4-post rack mounting
brackets to secure the air duct mounting brackets with 4-post mounting brackets
together.
4.
Secure the air-duct mounting bracket to the rack chassis with M3.5 screws. Torque
the screws to approximately 1.1 Nm ± 0.1 Nm (10 inch-pounds).
5.
Plug the power cords into their respective NE2580O power connectors and using
tie wraps, secure the power cords to the mounting rails.
M3.5 screws
Air duct mounting bracket
M6 screws
Tie wraps
Tie wraps
Power connection
Power connection
Summary of Contents for ThinkSystem NE2580O RackSwitch
Page 1: ...Lenovo ThinkSystem NE2580O RackSwitch Installation Guide For Network Operating System ...
Page 6: ...6 Lenovo NE2580O Installation Guide ...
Page 14: ...14 NE2580O Installation Guide ...
Page 54: ...54 NE2580O Installation Guide ...
Page 70: ...70 NE2580O Installation Guide ...
Page 88: ...88 NE2580O Installation Guide ...