5.1 Assembly instructions
1. Before incorporating the counter into the control panel the installation frame
(see dimensioned drawing in chapter 6) must be pulled off the counter
housing. For this purpose slightly lift the 4 catch brackets (alternately on top
and at the bottom, and pushing them forward catch by catch).
2. Turn back the screws of the installation frame by approx. 5 mm.
3. Insert counter into the cut-out of panel and snap installation frame into place.
4. Fix the counter with the screws against the panel (free from play).
5.2 Commissioning
Before setting the counter into operation check whether you can answer the
following questions with yes:
✔
Does the supply voltage rating correspond to the voltage specified at the
counter?
✔
Has the supply voltage been connected to the correct terminals and is the
polarity correct for DC supply?
✔
The maximum counter frequency will not be exceeded?
✔
Have the control pulses for the counter got the necessary switching
thresholds (see para. 6.2)?
✔
Has programming been performed properly, i.e. according to the specific
requirements?